stroomstoring

Power failure: Arnhem-Duisburg-Düsseldorf (25 July 2019)

  1. Disruption resolved Last update

    Between Zevenaar and Emmerich the train traffic is fully resumed.

  2. Delays decreasing

    Between Zevenaar and Emmerich the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 9:00 AM hours.

  3. Disruption

    Between Zevenaar and Emmerich there is a service disruption due to a power failure.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 8:24 AM on July 25, 2019 and took 20 minutes in total.

For statistics, this disruption is caused due to a power failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS International, Deutsche Bahn and Abellio.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights