stroomstoring

Power failure: Roosendaal-Vlissingen (25 July 2019)

  1. Disruption resolved Last update

    Between Bergen op Zoom and Goes the train traffic is fully resumed.

  2. Delays decreasing

    Between Bergen op Zoom and Goes the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 5:30 PM hours.

  3. Update

    Between Bergen op Zoom and Goes no trains are running due to a power failure.
    The extra travel time may be up to 60 minutes.
    This will take until at least 6:00 PM hours.

    Advice

    Buses are running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Kruiningen-Yerseke and Goes
  4. Update

    Between Bergen op Zoom and Goes no trains are running due to a power failure.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 5:00 PM hours.

    Advice

    Buses are running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Kruiningen-Yerseke and Goes
  5. Update

    Between Bergen op Zoom and Vlissingen no trains are running due to a power failure.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 5:00 PM hours.

    Advice

    Buses are running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Kruiningen-Yerseke and Goes
  6. Update

    Between Kruiningen-Yerseke and Goes no trains are running due to a power failure.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 5:00 PM hours.

    Advice

    Buses are running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Kruiningen-Yerseke and Goes
  7. Update

    Between Kruiningen-Yerseke and Goes no trains are running due to a power failure.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 5:00 PM hours.

    Advice

    Buses are running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Bergen op Zoom and Vlissingen
  8. Update

    Between Bergen op Zoom and Vlissingen no trains are running due to a power failure.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 4:30 PM hours.

    Advice

    Buses are running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Bergen op Zoom and Vlissingen
  9. Update

    Between Bergen op Zoom and Goes no trains are running due to a power failure.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 4:30 PM hours.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Bergen op Zoom and Goes
  10. Update

    Between Bergen op Zoom and Goes no trains are running due to a power failure.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 4:30 PM hours.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Bergen op Zoom and Kruiningen-Yerseke
  11. Update

    Between Bergen op Zoom and Goes no trains are running due to a power failure.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 2:45 PM hours.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Bergen op Zoom and Kruiningen-Yerseke
  12. Update

    Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to a power failure.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 2:45 PM hours.

    Train measures

    • Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Bergen op Zoom and Kruiningen-Yerseke
  13. Update

    Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to a power failure.
    The extra travel time may be up to 60 minutes.
    This will take until approximately 2:45 PM hours.

  14. Update

    Between Bergen op Zoom and Kruiningen-Yerseke there is a service disruption due to a power failure.
    Updates will follow as more information becomes available.

  15. Disruption

    Between Bergen op Zoom and Kruiningen-Yerseke there is a service disruption due to a signal failure.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 12:32 PM on July 25, 2019 and took 4 hours, 50 minutes in total.

For statistics, this disruption is caused due to a power failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights