Defective railway track: Roosendaal-Vlissingen (7 August 2019)
-
Disruption resolved Last update
Between Bergen op Zoom and Kruiningen-Yerseke the train traffic is fully resumed.
Train measures
- Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Bergen op Zoom and Kruiningen-Yerseke
-
Update
Between Bergen op Zoom and Kruiningen-Yerseke there are fewer trains running due to a defective railway track.
The extra travel time may be up to 30 minutes.
This will take until approximately 1:00 AM on Thursday, August 8, 2019.Train measures
- Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Bergen op Zoom and Kruiningen-Yerseke
-
Update
Between Bergen op Zoom and Kruiningen-Yerseke there are fewer trains running due to a defective railway track.
The extra travel time may be up to 30 minutes.
This will take the rest of the day.Train measures
- Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Bergen op Zoom and Kruiningen-Yerseke
-
Update
Between Bergen op Zoom and Kruiningen-Yerseke there are fewer trains running due to a defective railway track.
The extra travel time may be up to 30 minutes.
This will take the rest of the day.Advice
Local buses are running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.
Train measures
- Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Bergen op Zoom and Kruiningen-Yerseke
-
Update
Between Bergen op Zoom and Kruiningen-Yerseke there are fewer trains running due to a defective railway track.
The extra travel time may be up to 30 minutes.
This will take until approximately 8:30 PM hours.Advice
Local buses are running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.
Train measures
- Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Bergen op Zoom and Kruiningen-Yerseke
-
Update
Between Bergen op Zoom and Kruiningen-Yerseke there are fewer trains running due to a defective railway track.
The extra travel time may be up to 30 minutes.
This will take until at least 6:00 PM hours.Advice
Local buses are running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.
Train measures
- Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Bergen op Zoom and Kruiningen-Yerseke
-
Update
Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to a defective railway track.
The extra travel time is more than 60 minutes.
This will take until at least 6:00 PM hours.Advice
Local buses are running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.
Train measures
- Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Bergen op Zoom and Kruiningen-Yerseke
-
Update
Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to a defective railway track.
The extra travel time is more than 30 minutes.
This will take until at least 6:00 PM hours.Advice
Local buses are running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.
Train measures
- Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Bergen op Zoom and Kruiningen-Yerseke
-
Update
Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to a defective railway track.
The extra travel time is more than 60 minutes.
This will take until at least 6:00 PM hours.Advice
Local buses are running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.
Train measures
- Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Bergen op Zoom and Kruiningen-Yerseke
-
Update
Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to a defective railway track.
The extra travel time is more than 60 minutes.
This will take until at least 6:00 PM hours.Train measures
- Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Bergen op Zoom and Kruiningen-Yerseke
-
Update
Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to a defective railway track.
The extra travel time is more than 60 minutes.
This will take until at least 6:30 PM hours.Train measures
- Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Bergen op Zoom and Kruiningen-Yerseke
-
Update
Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to a defective railway track.
The extra travel time is more than 60 minutes.
This will take until at least 6:00 PM hours.Train measures
- Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Bergen op Zoom and Kruiningen-Yerseke
-
Update
Between Bergen op Zoom and Kruiningen-Yerseke there are fewer trains running due to a defective railway track.
The extra travel time may be up to 30 minutes.
This will take until at least 6:00 PM hours.Train measures
- Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen runs only once per hour between Bergen op Zoom and Kruiningen-Yerseke
-
Update
Between Bergen op Zoom and Kruiningen-Yerseke there are delays and fewer trains are running due to a defective railway track.
This will take until at least 6:00 PM hours. -
Disruption
Between Bergen op Zoom and Kruiningen-Yerseke there are delays and fewer trains are running due to a defective railway track.
It is not known yet how long this will take.
More about this disruption
Statistics
This disruption started at 12:20 PM on August 7, 2019 and took 12 hours, 22 minutes in total.
For statistics, this disruption is caused due to a defective railway track.
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.