Damaged railway bridge: Alkmaar-Den Helder; Alkmaar-Hoorn (19 August 2019)
-
Disruption resolved Last update
Between Alkmaar and Heerhugowaard the train traffic is fully resumed.
-
Delays decreasing
Between Alkmaar and Heerhugowaard the restrictions are resolved.
Delays are decreasing.
Service is normal around 10:00 PM hours. -
Delays decreasing
Between Alkmaar and Heerhugowaard the restrictions are resolved.
Delays are decreasing.
Service is normal around 10:00 PM hours.Train measures
- Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Alkmaar and Heerhugowaard
- Sprinter 4800 Amsterdam C. - Haarlem - Hoorn is cancelled between Alkmaar and Heerhugowaard
-
Update
Between Alkmaar and Heerhugowaard no trains are running due to a damaged railway bridge.
This will take until at least 10:45 PM hours.Train measures
- Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Alkmaar and Heerhugowaard
- Sprinter 4800 Amsterdam C. - Haarlem - Hoorn is cancelled between Alkmaar and Heerhugowaard
-
Update
Between Alkmaar and Heerhugowaard no trains are running due to a damaged railway bridge.
This will take until at least 10:45 PM hours. -
Disruption
Between Alkmaar and Heerhugowaard no trains are running due to a damaged railway bridge.
This will take until at least 10:45 PM hours.
More about this disruption
Statistics
This disruption started at 9:11 PM on August 19, 2019 and took 41 minutes in total.
For statistics, this disruption is caused due to a damaged railway bridge.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.