Flooding: Maastricht-Liège / Luik (9 September 2019)

  1. Disruption resolved Last update

    Between Maastricht Randwyck and Visé the train traffic is fully resumed.

  2. Delays decreasing

    Between Maastricht Randwyck and Visé the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 9:45 PM hours.

  3. Update

    Between Maastricht Randwyck and Visé far fewer trains are running due to flooding.
    It is not known yet how long this will take.

    Train measures

    • Stoptrein 5300 Maastricht - Liège-Guillemins is cancelled between Maastricht and Visé
  4. Disruption

    Between Maastricht Randwyck and Visé no trains are running due to flooding.
    It is not known yet how long this will take.

    Train measures

    • Stoptrein 5300 Maastricht - Liège-Guillemins is cancelled between Maastricht and Visé
  5. Update

    Between Maastricht Randwyck and Visé no trains are running due to railway problems abroad.
    It is not known yet how long this will take.

    Train measures

    • Stoptrein 5300 Maastricht - Liège-Guillemins is cancelled between Maastricht and Visé

More about this disruption

Statistics

This disruption started at 6:16 PM on September 9, 2019 and took 3 hours, 29 minutes in total.

For statistics, this disruption is caused due to flooding.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NMBS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights