    Between Sauwerd and Warffum the train traffic is fully resumed.

  2. Delays decreasing

    Between Sauwerd and Warffum the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 8:15 AM hours.

  3. Update

    Between Sauwerd and Warffum there are fewer trains running due to a level crossing failure.
    The extra travel time is about 30 minutes.
    This will take until approximately 8:30 AM hours.

  4. Update

    Between Sauwerd and Warffum there are fewer trains running due to a level crossing failure.
    The extra travel time is about 30 minutes.
    This will take until approximately 8:30 AM hours.

    Train measures

    • Stoptrein 37600 Groningen - Eemshaven is cancelled between Groningen and Roodeschool
  5. Update

    Between Sauwerd and Warffum no trains are running due to a level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 7:30 AM hours.

    Train measures

    • Stoptrein 37600 Groningen - Eemshaven is cancelled between Groningen and Roodeschool
  6. Update

    Between Sauwerd and Warffum no trains are running due to a level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 10:00 AM hours.

    Train measures

    • Stoptrein 37600 Groningen - Eemshaven is cancelled between Groningen and Roodeschool
  7. Update

    Between Baflo and Warffum there are fewer trains running due to a level crossing failure.
    This will take until approximately 10:00 AM hours.

  8. Disruption resolved

    Between Baflo and Warffum the train traffic is fully resumed.

  9. Disruption

    Between Baflo and Warffum there is a service disruption due to a level crossing failure.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 5:23 AM on October 15, 2019 and took 2 hours, 43 minutes in total.

For statistics, this disruption is caused due to a level crossing failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by Arriva.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights