overwegstoring

Level crossing failure: Roermond-Sittard (18 October 2019)

  1. Disruption resolved Last update

    Between Roermond and Sittard the train traffic is fully resumed.

  2. Delays decreasing

    Between Roermond and Sittard the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 10:30 AM hours.

    Advice

    Local buses are still running between Roermond, Echt, Susteren and Sittard.

  3. Update

    Between Roermond and Sittard no trains are running due to a level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 11:00 AM hours.

    Advice

    Local buses are running between Roermond, Echt, Susteren and Sittard.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven - Maastricht is cancelled between Roermond and Sittard
    • Intercity 3900 Enkhuizen - Utrecht C. - Eindhoven - Heerlen is cancelled between Roermond and Sittard
    • Stoptrein 32400 Roermond - Maastricht - Randwyck is cancelled between Roermond and Sittard
  4. Update

    Between Roermond and Sittard no trains are running due to a level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 11:00 AM hours.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven - Maastricht is cancelled between Roermond and Sittard
    • Intercity 3900 Enkhuizen - Utrecht C. - Eindhoven - Heerlen is cancelled between Roermond and Sittard
    • Stoptrein 32400 Roermond - Maastricht - Randwyck is cancelled between Roermond and Sittard
  5. Update

    Between Roermond and Susteren no trains are running due to a level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 11:00 AM hours.

  6. Disruption

    Between Roermond and Sittard there is a service disruption due to a level crossing failure.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 8:35 AM on October 18, 2019 and took 1 hour, 53 minutes in total.

For statistics, this disruption is caused due to a level crossing failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS and Arriva.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights