Signal and level crossing failure: Alkmaar-Den Helder (18 October 2019)
-
Disruption resolved Last update
Between Schagen and Anna Paulowna the train traffic is fully resumed.
-
Delays decreasing
Between Schagen and Anna Paulowna the restrictions are resolved.
Delays are decreasing.
Service is normal around 12:15 AM on Saturday, October 19, 2019.Advice
Buses are still running between Schagen and Anna Paulowna.
-
Update
Between Schagen and Anna Paulowna no trains are running due to a signal and level crossing failure.
The extra travel time is about 30 minutes.
This will take until approximately 12:15 AM on Saturday, October 19, 2019.Advice
Buses are running between Schagen and Anna Paulowna.
Train measures
- Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Schagen and Anna Paulowna
-
Update
Between Schagen and Anna Paulowna no trains are running due to a signal and level crossing failure.
The extra travel time is about 30 minutes.
This will take until at least 12:15 AM on Saturday, October 19, 2019.Advice
Buses are running between Schagen and Anna Paulowna.
Train measures
- Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Schagen and Anna Paulowna
-
Update
Between Schagen and Anna Paulowna no trains are running due to a signal and level crossing failure.
The extra travel time is about 30 minutes.
This will take until approximately 12:15 AM on Saturday, October 19, 2019.Advice
Buses are running between Schagen and Anna Paulowna.
Train measures
- Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Schagen and Anna Paulowna
-
Update
Between Schagen and Anna Paulowna no trains are running due to a signal and level crossing failure.
The extra travel time is about 30 minutes.
This will take until approximately 10:00 PM hours.Advice
Buses are running between Schagen and Anna Paulowna.
Train measures
- Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Schagen and Anna Paulowna
-
Update
Between Schagen and Anna Paulowna no trains are running due to a signal and level crossing failure.
The extra travel time is about 30 minutes.
This will take until approximately 9:00 PM hours.Advice
Buses are running between Schagen and Anna Paulowna.
Train measures
- Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Schagen and Anna Paulowna
-
Update
Between Schagen and Anna Paulowna no trains are running due to a signal and level crossing failure.
The extra travel time is about 30 minutes.
This will take until approximately 8:30 PM hours.Advice
Buses are running between Schagen and Anna Paulowna.
Train measures
- Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Schagen and Anna Paulowna
-
Update
Between Schagen and Anna Paulowna no trains are running due to a signal and level crossing failure.
The extra travel time is more than 60 minutes.
This will take until approximately 8:30 PM hours.Train measures
- Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Schagen and Anna Paulowna
-
Update
Between Schagen and Anna Paulowna no trains are running due to a signal and level crossing failure.
The extra travel time is more than 60 minutes.
This will take until approximately 9:00 PM hours.Train measures
- Intercity 3000 Den Helder - Amsterdam C. - Utrecht C. - Nijmegen is cancelled between Schagen and Anna Paulowna
-
Update
Between Schagen and Anna Paulowna no trains are running due to a signal and level crossing failure.
The extra travel time is more than 60 minutes.
This will take until approximately 9:00 PM hours. -
Update
Between Schagen and Anna Paulowna no trains are running due to a signal and level crossing failure.
The extra travel time is more than 60 minutes.
This will take until approximately 7:30 PM hours. -
Disruption
Between Schagen and Anna Paulowna there is a service disruption due to a signal and level crossing failure.
Updates will follow as more information becomes available.
More about this disruption
Statistics
This disruption started at 5:44 PM on October 18, 2019 and took 6 hours, 31 minutes in total.
For statistics, this disruption is caused due to a signal and level crossing failure.
Operators
This disruption affects trains operated by NS.