beschadigde bovenleiding

Damaged overhead wires: Breda (19 December 2019)

  1. Disruption resolved Last update

    From and to Breda the train traffic is fully resumed.

  2. Delays decreasing

    From and to Breda the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 6:30 PM hours.

  3. Update

    From and to Breda no international trains are running due to damaged overhead wires.
    Service is normal around 6:30 PM hours.

    Advice

    Buses are running between Breda and Noorderkempen.

  4. Update

    From and to Breda no international trains are running due to damaged overhead wires.
    Service is normal around 5:00 PM hours.

    Advice

    Buses are running between Breda and Noorderkempen.

  5. Disruption resolved

    From and to Breda the train traffic is fully resumed.

  6. Delays decreasing

    From and to Breda the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 4:45 PM hours.

  7. Update

    From and to Breda no international trains are running due to damaged overhead wires.
    The extra travel time may be up to 30 minutes.
    This will take until at least 5:00 PM hours.

    Advice

    Buses are running between Breda and Noorderkempen.

    Train measures

    • Intercity direct 9200-9211 Amsterdam C. - Rotterdam C. - Antwerpen-C. - Brussel Z./Midi is diverted and will not call at Breda between Rotterdam Centraal and Noorderkempen
  8. Update

    From and to Breda no international trains are running due to damaged overhead wires.
    The extra travel time may be up to 30 minutes.
    This will take until at least 4:00 PM hours.

    Advice

    Buses are running between Breda and Noorderkempen.

    Train measures

    • Intercity direct 9200-9211 Amsterdam C. - Rotterdam C. - Antwerpen-C. - Brussel Z./Midi is diverted and will not call at Breda between Rotterdam Centraal and Noorderkempen
  9. Update

    From and to Breda no international trains are running due to damaged overhead wires.
    The extra travel time may be up to 30 minutes.
    This will take until at least 2:00 PM hours.

    Advice

    Buses are running between Breda and Noorderkempen.

    Train measures

    • Intercity direct 9200-9211 Amsterdam C. - Rotterdam C. - Antwerpen-C. - Brussel Z./Midi is diverted and will not call at Breda between Rotterdam Centraal and Noorderkempen
  10. Disruption

    From and to Breda no international trains are running due to damaged overhead wires.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 5:00 PM hours.

    Advice

    Buses are running between Breda and Noorderkempen.

    Train measures

    • Intercity direct 9200-9211 Amsterdam C. - Rotterdam C. - Antwerpen-C. - Brussel Z./Midi is diverted and will not call at Breda between Rotterdam Centraal and Noorderkempen

More about this disruption

Statistics

This disruption started at 10:51 AM on December 19, 2019 and took 7 hours, 17 minutes in total.

For statistics, this disruption is caused due to damaged overhead wires.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS, NS International and NMBS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights