overwegstoring

Level crossing failure: Roermond-Sittard (25 December 2019)

  1. Disruption resolved Last update

    Between Roermond and Sittard the train traffic is fully resumed.

  2. Delays decreasing

    Between Roermond and Sittard the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 3:15 PM hours.

  3. Delays decreasing

    Between Roermond and Sittard the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 2:45 PM hours.

  4. Update

    Between Roermond and Sittard far fewer trains are running due to a level crossing failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 3:00 PM hours.

    Train measures

    • Intercity 3900 Enkhuizen - Utrecht C. - Eindhoven C. - Heerlen is cancelled between Roermond and Sittard
    • Stoptrein 32400 Roermond - Maastricht - Randwyck is cancelled between Roermond and Sittard
    • Stoptrein 32400 Roermond - Maastricht - Randwyck is cancelled between Roermond and Swalmen
  5. Update

    Between Roermond and Sittard far fewer trains are running due to a level crossing failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 2:30 PM hours.

    Train measures

    • Intercity 3900 Enkhuizen - Utrecht C. - Eindhoven C. - Heerlen is cancelled between Roermond and Sittard
    • Stoptrein 32400 Roermond - Maastricht - Randwyck is cancelled between Roermond and Swalmen
    • Stoptrein 32400 Roermond - Maastricht - Randwyck is cancelled between Roermond and Sittard
  6. Update

    Between Roermond and Sittard far fewer trains are running due to a level crossing failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 6:30 PM hours.

    Train measures

    • Intercity 3900 Enkhuizen - Utrecht C. - Eindhoven C. - Heerlen is cancelled between Roermond and Sittard
    • Stoptrein 32400 Roermond - Maastricht - Randwyck is cancelled between Roermond and Swalmen
    • Stoptrein 32400 Roermond - Maastricht - Randwyck is cancelled between Roermond and Sittard
  7. Update

    Between Susteren and Sittard there is a service disruption due to a level crossing failure.
    Updates will follow as more information becomes available.

    Train measures

    • Intercity 3900 Enkhuizen - Utrecht C. - Eindhoven C. - Heerlen is cancelled between Roermond and Sittard
    • Stoptrein 32400 Roermond - Maastricht - Randwyck is cancelled between Roermond and Sittard
    • Stoptrein 32400 Roermond - Maastricht - Randwyck is cancelled between Roermond and Swalmen
  8. Disruption

    Between Susteren and Sittard there is a service disruption due to a level crossing failure.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 1:29 PM on December 25, 2019 and took 1 hour, 45 minutes in total.

For statistics, this disruption is caused due to a level crossing failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS and Arriva.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights