Disruption resolved Last update
Between Leiden Centraal and Lelystad Centrum the train traffic is fully resumed.
-
Delays decreasing
Between Leiden Centraal and Lelystad Centrum the restrictions are resolved.
Delays are decreasing.
Service is normal around 3:00 PM hours. -
Update
Between Leiden Centraal and Lelystad Centrum fewer intercities are running due to an earlier disruption.
The extra travel time may be up to 15 minutes.
Service is normal around 3:00 PM hours.Train measures
- Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Den Haag HS and Lelystad Centrum
-
Update
Between Leiden Centraal and Lelystad Centrum fewer intercities are running due to an earlier disruption.
The extra travel time may be up to 15 minutes.
This will take until approximately 1:00 PM hours.Train measures
- Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Den Haag HS and Lelystad Centrum
-
Disruption
Between Amsterdam RAI and Almere Poort fewer intercities are running due to an earlier disruption.
The extra travel time may be up to 15 minutes.
This will take until approximately 1:00 PM hours.Train measures
- Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Den Haag HS and Lelystad Centrum
More about this disruption
Statistics
This disruption started at 10:54 AM on January 30, 2020 and took 4 hours, 7 minutes in total.
For statistics, this disruption is caused due to an earlier disruption.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.