Collision: Rotterdam-Gouda (9 February 2020)
-
Disruption resolved Last update
Between Rotterdam Alexander and Nieuwerkerk a/d IJssel the train traffic is fully resumed.
-
Delays decreasing
Between Rotterdam Alexander and Nieuwerkerk a/d IJssel the restrictions are resolved.
Delays are decreasing.
Service is normal around 3:15 PM hours. -
Disruption
Between Rotterdam Alexander and Nieuwerkerk a/d IJssel there is a service disruption due to a collision.
Updates will follow as more information becomes available.
More about this disruption
Statistics
This disruption started at 2:40 PM on February 9, 2020 and took 36 minutes in total.
For statistics, this disruption is caused due to a collision.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.