Collision: Leiden-Den Haag HS; Leiden-Den Haag C (6 April 2020)
-
Disruption resolved Last update
Between Leiden Centraal and Den Haag Laan v NOI the train traffic is fully resumed.
-
Delays decreasing
Between Leiden Centraal and Den Haag Laan v NOI the restrictions are resolved.
Delays are decreasing.
Service is normal around 7:45 AM hours.Train measures
- Sprinter 4600 Den Haag C. - Schiphol Airport - Amsterdam C. is cancelled between Leiden Centraal and Den Haag Centraal
- Sprinter 6300 Den Haag C. - Leiden C. - Haarlem is cancelled between Leiden Centraal and Den Haag Centraal
-
Delays decreasing
Between Leiden Centraal and Den Haag Laan v NOI the restrictions are resolved.
Delays are decreasing.
Service is normal around 8:00 AM hours.Train measures
- Sprinter 4600 Den Haag C. - Schiphol Airport - Amsterdam C. is cancelled between Leiden Centraal and Den Haag Centraal
- Sprinter 6300 Den Haag C. - Leiden C. - Haarlem is cancelled between Leiden Centraal and Den Haag Centraal
-
Update
Between Leiden Centraal and Den Haag Laan v NOI no trains are running due to a collision.
This will take until at least 8:00 AM hours.Train measures
- Sprinter 4600 Den Haag C. - Schiphol Airport - Amsterdam C. is cancelled between Leiden Centraal and Den Haag Centraal
- Sprinter 6300 Den Haag C. - Leiden C. - Haarlem is cancelled between Leiden Centraal and Den Haag Centraal
-
Update
Between Leiden Centraal and Den Haag Laan v NOI no trains are running due to a collision.
This will take until at least 8:00 AM hours. -
Update
Between Leiden Centraal and Den Haag Laan v NOI no trains are running due to a collision.
This will take until at least 9:00 AM hours.Train measures
- Sprinter 4600 Den Haag C. - Schiphol Airport - Amsterdam C. is cancelled between Leiden Centraal and Den Haag Centraal
- Sprinter 6300 Den Haag C. - Leiden C. - Haarlem is cancelled between Leiden Centraal and Den Haag Centraal
-
Disruption
Between Leiden Centraal and Den Haag Laan v NOI no trains are running due to a collision.
This will take until at least 9:00 AM hours.
More about this disruption
Statistics
This disruption started at 6:08 AM on April 6, 2020 and took 1 hour, 36 minutes in total.
For statistics, this disruption is caused due to a collision.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.