Points failure: Den Haag-Gouda Goverwelle (16 June 2020)
-
Disruption resolved Last update
Between Gouda Goverwelle and Den Haag Centraal the train traffic is fully resumed.
-
Delays decreasing
Between Gouda Goverwelle and Den Haag Centraal the restrictions are resolved.
Delays are decreasing.
Service is normal around 3:30 PM hours. -
Update
Between Gouda Goverwelle and Den Haag Centraal no Sprinters are running due to a points failure.
The extra travel time is more than 60 minutes.
This will take until approximately 4:45 PM hours.Advice
Postpone your journey. This way we can prevent overcrowding at stations and replacement transport together.
Train measures
- Sprinter 6900 Den Haag C. - Utrecht C. - 's-Hertogenbosch is cancelled between Den Haag Centraal and Gouda Goverwelle
-
Update
Between Gouda Goverwelle and Den Haag Centraal no Sprinters are running due to a points failure.
The extra travel time is more than 60 minutes.
This will take until approximately 4:45 PM hours.Train measures
- Sprinter 6900 Den Haag C. - Utrecht C. - 's-Hertogenbosch is cancelled between Den Haag Centraal and Gouda Goverwelle
-
Update
Between Voorburg and Den Haag Centraal there are fewer trains running due to a points failure.
The extra travel time is about 30 minutes.
This will take until approximately 4:45 PM hours. -
Disruption
Between Voorburg and Den Haag Centraal there is a service disruption due to a points failure.
Updates will follow as more information becomes available.
More about this disruption
Statistics
This disruption started at 2:04 PM on June 16, 2020 and took 1 hour, 21 minutes in total.
For statistics, this disruption is caused due to a points failure.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.