wisselstoring

Points failure: Amsterdam-Köln-Frankfurt (25 June 2020)

  1. Disruption resolved Last update

    Between Utrecht Centraal and Arnhem Centraal the train traffic is fully resumed.

  2. Delays decreasing

    Between Utrecht Centraal and Arnhem Centraal the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 6:00 PM hours.

  3. Update

    Between Utrecht Centraal and Arnhem Centraal international trains will run an alternative route due to a points failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 6:00 PM hours.

  4. Disruption

    Between Utrecht Centraal and Arnhem Centraal international trains will run an alternative route due to a points failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 4:45 PM hours.

More about this disruption

Statistics

This disruption started at 2:46 PM on June 25, 2020 and took 3 hours, 11 minutes in total.

For statistics, this disruption is caused due to a points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS and NS International.