overwegstoring

Level crossing failure: Groningen-Delfzijl (29 June 2020)

  1. Disruption resolved Last update

    Between Sauwerd and Delfzijl the train traffic is fully resumed.

  2. Delays decreasing

    Between Sauwerd and Delfzijl the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 9:00 PM hours.

    Advice

    Local buses are still running between Sauwerd, Bedum, Stedum, Loppersum, Appingedam, Delfzijl West and Delfzijl.

  3. Update

    Between Sauwerd and Delfzijl no trains are running due to a level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 9:30 PM hours.

    Advice

    Local buses are running between Sauwerd, Bedum, Stedum, Loppersum, Appingedam, Delfzijl West and Delfzijl.

    Train measures

    • Stoptrein 37600 Groningen - Eemshaven keeps running normally between Groningen and Roodeschool
    • Stoptrein 37700 Groningen - Delfzijl is cancelled between Groningen and Delfzijl
  4. Update

    Between Sauwerd and Delfzijl no trains are running due to a level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 8:30 PM hours.

    Advice

    Local buses are running between Sauwerd, Bedum, Stedum, Loppersum, Appingedam, Delfzijl West and Delfzijl.

    Train measures

    • Stoptrein 37600 Groningen - Eemshaven keeps running normally between Groningen and Roodeschool
    • Stoptrein 37700 Groningen - Delfzijl is cancelled between Groningen and Delfzijl
  5. Update

    Between Sauwerd and Bedum no trains are running due to a level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 8:30 PM hours.

    Train measures

    • Stoptrein 37700 Groningen - Delfzijl is cancelled between Groningen and Delfzijl
  6. Update

    Between Groningen and Bedum no trains are running due to a level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 8:30 PM hours.

    Train measures

    • Stoptrein 37700 Groningen - Delfzijl is cancelled between Groningen and Delfzijl
  7. Update

    Between Groningen and Bedum no trains are running due to a level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 8:30 PM hours.

  8. Update

    Between Sauwerd and Delfzijl there is a service disruption due to a level crossing failure.
    Updates will follow as more information becomes available.

  9. Update

    Between Sauwerd and Stedum there is a service disruption due to a level crossing failure.
    Updates will follow as more information becomes available.

  10. Disruption

    Between Groningen and Sauwerd there is a service disruption due to a level crossing failure.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 6:22 PM on June 29, 2020 and took 2 hours, 28 minutes in total.

For statistics, this disruption is caused due to a level crossing failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by Arriva.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights