Signal failure: Den Haag-Rotterdam (29 July 2020)

  1. Disruption resolved Last update

    Between Den Haag Centraal and Rotterdam Centraal the train traffic is fully resumed.

  2. Delays decreasing

    Between Den Haag Centraal and Rotterdam Centraal the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 8:00 PM hours.

  3. Update

    Between Den Haag Centraal and Rotterdam Centraal there are fewer trains running due to a signal failure.
    Service is normal around 8:00 PM hours.

    Advice

    Passengers between Den Haag Centraal and Rotterdam Centraal may also travel via Gouda. The extra travel time is up to 30 minutes.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Den Haag Centraal and Rotterdam Centraal
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
  4. Update

    Between Den Haag Centraal and Rotterdam Centraal there are fewer trains running due to a signal failure.
    This will take until at least 8:00 PM hours.

    Advice

    Passengers between Den Haag Centraal and Rotterdam Centraal may also travel via Gouda. The extra travel time is up to 30 minutes.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Den Haag Centraal and Rotterdam Centraal
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
  5. Update

    Between Den Haag Centraal and Rotterdam Centraal there are fewer trains running due to a signal failure.
    This will take until at least 7:00 PM hours.

    Advice

    Passengers between Den Haag Centraal and Rotterdam Centraal may also travel via Gouda. The extra travel time is up to 30 minutes.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Den Haag Centraal and Rotterdam Centraal
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
  6. Update

    Between Den Haag Centraal and Rotterdam Centraal there are fewer trains running due to a signal failure.
    This will take until at least 7:00 PM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Den Haag Centraal and Rotterdam Centraal
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
  7. Update

    Between Den Haag Centraal and Rotterdam Centraal far fewer trains are running due to a signal failure.
    This will take until at least 7:00 PM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Den Haag Centraal and Rotterdam Centraal
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
  8. Update

    Between Den Haag Centraal and Rotterdam Centraal far fewer trains are running due to a signal and level crossing failure.
    This will take until at least 7:00 PM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Den Haag Centraal and Rotterdam Centraal
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
  9. Update

    Between Den Haag Centraal and Rotterdam Centraal far fewer trains are running due to a signal and level crossing failure.
    This will take until at least 6:00 PM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Den Haag Centraal and Rotterdam Centraal
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
  10. Update

    Between Den Haag Centraal and Rotterdam Centraal far fewer trains are running due to a signal and level crossing failure.
    This will take until at least 5:45 PM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Den Haag Centraal and Rotterdam Centraal
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
  11. Update

    Between Den Haag Centraal and Rotterdam Centraal far fewer trains are running due to a signal and level crossing failure.
    This will take until at least 5:00 PM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Den Haag Centraal and Rotterdam Centraal
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
  12. Update

    Between Den Haag Centraal and Rotterdam Centraal there are fewer trains running due to a signal and level crossing failure.
    This will take until at least 5:00 PM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Den Haag Centraal and Rotterdam Centraal
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
  13. Update

    Between Den Haag Centraal and Rotterdam Centraal there are fewer trains running due to a signal and level crossing failure.
    This will take until at least 5:00 PM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Den Haag Centraal
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
  14. Update

    Between Den Haag Centraal and Rotterdam Centraal there are fewer trains running due to a signal and level crossing failure.
    This will take until approximately 5:00 PM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Den Haag Centraal
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
  15. Update

    Between Den Haag Centraal and Rotterdam Centraal far fewer trains are running due to a signal and level crossing failure.
    This will take until approximately 5:00 PM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Den Haag Centraal
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
  16. Update

    Between Den Haag Centraal and Rotterdam Centraal there are delays and fewer trains are running due to a signal and level crossing failure.
    This will take until approximately 5:00 PM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Den Haag Centraal
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
  17. Update

    Between Rotterdam Centraal and Den Haag Centraal there are delays and fewer trains are running due to a signal and level crossing failure.
    This will take until approximately 5:00 PM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Den Haag Centraal
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
  18. Update

    Between Rotterdam Centraal and Den Haag Centraal there are delays and fewer trains are running due to a signal and level crossing failure.
    This will take until approximately 4:00 PM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Den Haag Centraal
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
  19. Update

    Between Rotterdam Centraal and Den Haag Centraal there are delays and fewer trains are running due to a signal and level crossing failure.
    This will take until approximately 3:30 PM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Den Haag Centraal
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
  20. Update

    Between Rotterdam Centraal and Den Haag Centraal there are delays and fewer trains are running due to a signal and level crossing failure.
    This will take until approximately 4:45 PM hours.

    Train measures

    • Intercity 1100 Den Haag C. - Rotterdam C. - Breda is cancelled between Rotterdam Centraal and Den Haag Centraal
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag Centraal and Schiedam Centrum
  21. Update

    Between Rotterdam Centraal and Den Haag Centraal there are delays and fewer trains are running due to a signal and level crossing failure.
    This will take until approximately 4:45 PM hours.

  22. Update

    Between Rotterdam Centraal and Den Haag HS there are delays and fewer trains are running due to a signal and level crossing failure.
    This will take until approximately 4:45 PM hours.

  23. Update

    Between Rotterdam Centraal and Den Haag HS there are delays and fewer trains are running due to a signal and level crossing failure.
    Updates will follow as more information becomes available.

  24. Disruption

    Between Delft and Den Haag HS there are delays and fewer trains are running due to a signal and level crossing failure.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 1:12 PM on July 29, 2020 and took 6 hours, 47 minutes in total.

For statistics, this disruption is caused due to a signal failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.