seinstoring

Signal failure: Alphen a/d Rijn-Gouda (11 August 2020)

  1. Disruption resolved Last update

    Between Alphen a/d Rijn and Boskoop the train traffic is fully resumed.

  2. Delays decreasing

    Between Alphen a/d Rijn and Boskoop the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 9:15 PM hours.

  3. Delays decreasing

    Between Alphen a/d Rijn and Boskoop the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 9:30 PM hours.

  4. Update

    Between Alphen a/d Rijn and Boskoop no trains are running due to a signal failure.
    This will take until approximately 9:30 PM hours.

    Train measures

    • Sprinter 8600 Gouda - Alphen a/d Rijn is cancelled between Alphen a/d Rijn and Boskoop
  5. Update

    Between Alphen a/d Rijn and Boskoop no trains are running due to a signal failure.
    This will take until approximately 11:45 PM hours.

    Train measures

    • Sprinter 8600 Gouda - Alphen a/d Rijn is cancelled between Alphen a/d Rijn and Boskoop
  6. Disruption

    Between Alphen a/d Rijn and Boskoop no trains are running due to a signal failure.
    This will take until approximately 11:45 PM hours.

More about this disruption

Statistics

This disruption started at 7:57 PM on August 11, 2020 and took 1 hour, 20 minutes in total.

For statistics, this disruption is caused due to a signal failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by R-net.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights