Collision: Nijmegen-'s-Hertogenbosch (3 September 2020)

  1. Disruption resolved Last update

    Between Oss and Ravenstein the train traffic is fully resumed.

  2. Delays decreasing

    Between Oss and Ravenstein the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 10:30 PM hours.

  3. Disruption

    Between Oss and Ravenstein no trains are running due to a collision.
    This will take until approximately 11:30 PM hours.

More about this disruption

Statistics

This disruption started at 10:19 PM on September 3, 2020 and took 5 minutes in total.

For statistics, this disruption is caused due to a collision.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.