Points failure: Amsterdam-Enkhuizen (10 January 2021)
-
Disruption resolved Last update
Between Hoorn Kersenboogerd and Hoogkarspel the train traffic is fully resumed.
-
Delays decreasing
Between Hoorn Kersenboogerd and Hoogkarspel the restrictions are resolved.
Delays are decreasing.
Service is normal around 10:00 PM hours. -
Delays decreasing
Between Hoorn Kersenboogerd and Hoogkarspel the restrictions are resolved.
Delays are decreasing.
Service is normal around 10:00 PM hours.Advice
Buses are still running between Hoorn Kersenboogerd and Hoogkarspel.
-
Update
Between Hoorn Kersenboogerd and Hoogkarspel no trains are running due to a points failure.
The extra travel time is more than 60 minutes.
This will take until approximately 9:30 PM hours.Advice
Buses are running between Hoorn Kersenboogerd and Hoogkarspel.
Train measures
- Intercity 2900 Enkhuizen - Utrecht C. - Eindhoven C. - Maastricht is cancelled between Hoorn and Hoogkarspel
- Intercity 3900 Enkhuizen - Utrecht C. - Eindhoven C. - Heerlen is cancelled between Hoorn and Hoogkarspel
-
Update
Between Hoorn Kersenboogerd and Hoogkarspel no trains are running due to a points failure.
The extra travel time is more than 60 minutes.
This will take until approximately 10:00 PM hours.Advice
Buses are running between Hoorn Kersenboogerd and Hoogkarspel.
Train measures
- Intercity 2900 Enkhuizen - Utrecht C. - Eindhoven C. - Maastricht is cancelled between Hoorn and Hoogkarspel
- Intercity 3900 Enkhuizen - Utrecht C. - Eindhoven C. - Heerlen is cancelled between Hoorn and Hoogkarspel
-
Update
Between Hoorn Kersenboogerd and Hoogkarspel no trains are running due to a points failure.
The extra travel time is more than 60 minutes.
This will take until approximately 10:00 PM hours.Train measures
- Intercity 2900 Enkhuizen - Utrecht C. - Eindhoven C. - Maastricht is cancelled between Hoorn and Hoogkarspel
- Intercity 3900 Enkhuizen - Utrecht C. - Eindhoven C. - Heerlen is cancelled between Hoorn and Hoogkarspel
-
Update
Between Hoorn Kersenboogerd and Hoogkarspel no trains are running due to a points failure.
The extra travel time is more than 60 minutes.
This will take until approximately 9:30 PM hours.Train measures
- Intercity 2900 Enkhuizen - Utrecht C. - Eindhoven C. - Maastricht is cancelled between Hoorn and Hoogkarspel
- Intercity 3900 Enkhuizen - Utrecht C. - Eindhoven C. - Heerlen is cancelled between Hoorn and Hoogkarspel
-
Update
Between Hoorn Kersenboogerd and Hoogkarspel no trains are running due to a points failure.
The extra travel time is more than 60 minutes.
This will take until approximately 9:00 PM hours.Train measures
- Intercity 2900 Enkhuizen - Utrecht C. - Eindhoven C. - Maastricht is cancelled between Hoorn and Hoogkarspel
- Intercity 3900 Enkhuizen - Utrecht C. - Eindhoven C. - Heerlen is cancelled between Hoorn and Hoogkarspel
-
Update
Between Hoorn Kersenboogerd and Hoogkarspel no trains are running due to a points failure.
The extra travel time is more than 60 minutes.
This will take until approximately 9:00 PM hours.Train measures
- Intercity 2900 Enkhuizen - Utrecht C. - Eindhoven C. - Maastricht is cancelled between Hoorn and Hoogkarspel
-
Update
Between Hoorn Kersenboogerd and Hoogkarspel no trains are running due to a points failure.
The extra travel time is more than 60 minutes.
This will take until approximately 10:00 PM hours.Train measures
- Intercity 2900 Enkhuizen - Utrecht C. - Eindhoven C. - Maastricht is cancelled between Hoorn and Hoogkarspel
-
Update
Between Hoorn and Hoogkarspel there is a service disruption due to a points failure.
This will take until approximately 10:00 PM hours. -
Update
Between Hoorn Kersenboogerd and Hoogkarspel there is a service disruption due to a points failure.
Between Hoorn and Hoogkarspel there is a service disruption due to a points failure.
This will take until approximately 10:00 PM hours. -
Disruption
Between Hoorn and Hoogkarspel there is a service disruption due to a points failure.
Between Hoorn Kersenboogerd and Hoogkarspel there is a service disruption due to a points failure.
This will take until approximately 10:00 PM hours. -
Update
Between Hoorn Kersenboogerd and Hoogkarspel there is a service disruption due to a points failure.
This will take until approximately 10:00 PM hours.
More about this disruption
Statistics
This disruption started at 7:23 PM on January 10, 2021 and took 2 hours, 24 minutes in total.
For statistics, this disruption is caused due to a points failure.
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.