wisselstoring

Points failure: Utrecht-Leiden (31 January 2021)

  1. Disruption resolved Last update

    Between Woerden and Bodegraven the train traffic is fully resumed.

  2. Delays decreasing

    Between Woerden and Bodegraven the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 10:45 AM hours.

  3. Delays decreasing

    Between Woerden and Bodegraven the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 10:45 AM hours.

    Advice

    Express buses are still running between Bodegraven and Woerden.

  4. Update

    Between Woerden and Bodegraven no trains are running due to a points failure.
    The first trains are expected to be running after 10:45 AM hours.

    Advice

    Express buses are running between Bodegraven and Woerden.

    Train measures

    • Intercity 8800 Leiden C. - Utrecht C. is cancelled between Bodegraven and Utrecht Centraal
  5. Update

    Between Woerden and Bodegraven no trains are running due to a points failure.
    This will take until approximately 11:00 AM hours.

    Train measures

    • Sprinter 6900 Den Haag C. - Utrecht C. - Tiel is cancelled between Den Haag Centraal and Gouda
    • Intercity 8800 Leiden C. - Utrecht C. is cancelled between Bodegraven and Utrecht Centraal
  6. Update

    Between Utrecht Centraal and Bodegraven no trains are running due to a points failure.
    This will take until approximately 11:00 AM hours.

    Train measures

    • Sprinter 6900 Den Haag C. - Utrecht C. - Tiel is cancelled between Den Haag Centraal and Gouda
    • Intercity 8800 Leiden C. - Utrecht C. is cancelled between Bodegraven and Utrecht Centraal
  7. Disruption

    Between Utrecht Centraal and Bodegraven no trains are running due to a points failure.
    This will take until approximately 11:00 AM hours.

    Train measures

    • Intercity 1700 Den Haag C. - Amersfoort C. - Hengelo - Enschede is cancelled between Den Haag Centraal and Utrecht Centraal
    • Sprinter 6900 Den Haag C. - Utrecht C. - Tiel is cancelled between Den Haag Centraal and Gouda
    • Intercity 8800 Leiden C. - Utrecht C. is cancelled between Bodegraven and Utrecht Centraal
    • Intercity 11700 Den Haag C. - Utrecht C. - Schothorst is cancelled between Den Haag Centraal and Utrecht Centraal

More about this disruption

Statistics

This disruption started at 8:55 AM on January 31, 2021 and took 1 hour, 46 minutes in total.

For statistics, this disruption is caused due to a points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights