Signal and level crossing failure: Alphen a/d Rijn-Gouda (28 April 2021)
-
Disruption resolved Last update
Between Boskoop and Gouda the train traffic is fully resumed.
-
Delays decreasing
Between Boskoop and Gouda the restrictions are resolved.
Delays are decreasing.
Service is normal around 11:15 PM hours. -
Delays decreasing
Between Boskoop and Gouda the restrictions are resolved.
Delays are decreasing.
Service is normal around 11:15 PM hours.Advice
Local buses are still running between Boskoop, Boskoop Snijdelwijk, Waddinxveen Noord, Waddinxveen, Waddinxveen Triangel and Gouda.
-
Update
Between Boskoop and Gouda no trains are running due to a signal and level crossing failure.
Service is normal around 11:15 PM hours.Advice
Local buses are running between Boskoop, Boskoop Snijdelwijk, Waddinxveen Noord, Waddinxveen, Waddinxveen Triangel and Gouda.
Train measures
- Sprinter 8600 Gouda - Alphen a/d Rijn is cancelled between Boskoop and Gouda
-
Update
Between Boskoop and Gouda no trains are running due to a signal and level crossing failure.
Service is normal around 11:15 PM hours.Advice
Local buses are running between Boskoop, Boskoop Snijdelwijk, Waddinxveen Noord, Waddinxveen, Waddinxveen Triangel and Gouda.
Passengers between Alphen a/d Rijn and Gouda may also travel via Woerden. The extra travel time is up to 15 minutes.Train measures
- Sprinter 8600 Gouda - Alphen a/d Rijn is cancelled between Boskoop and Gouda
-
Update
Between Boskoop and Gouda no trains are running due to a signal and level crossing failure.
Service is normal around 11:15 PM hours.Advice
Local buses are running between Boskoop, Boskoop Snijdelwijk, Waddinxveen Noord, Waddinxveen, Waddinxveen Triangel and Gouda.
Passengers between Alphen a/d Rijn and Gouda travel via Woerden. The extra travel time is up to 15 minutes.Train measures
- Sprinter 8600 Gouda - Alphen a/d Rijn is cancelled between Boskoop and Gouda
-
Update
Between Boskoop and Gouda no trains are running due to a signal and level crossing failure.
This will take until approximately 11:15 PM hours.Advice
Local buses are running between Boskoop, Boskoop Snijdelwijk, Waddinxveen Noord, Waddinxveen, Waddinxveen Triangel and Gouda.
Passengers between Alphen a/d Rijn and Gouda travel via Woerden. The extra travel time is up to 15 minutes.Train measures
- Sprinter 8600 Gouda - Alphen a/d Rijn is cancelled between Boskoop and Gouda
-
Update
Between Boskoop and Gouda no trains are running due to a signal and level crossing failure.
This will take until approximately 11:15 PM hours.Advice
Passengers between Alphen a/d Rijn and Gouda travel via Woerden. The extra travel time is up to 15 minutes.
Train measures
- Sprinter 8600 Gouda - Alphen a/d Rijn is cancelled between Boskoop and Gouda
-
Update
Between Boskoop and Gouda no trains are running due to a signal and level crossing failure.
This will take until approximately 1:30 AM on Thursday, April 29, 2021.Advice
Passengers between Alphen a/d Rijn and Gouda travel via Woerden. The extra travel time is up to 15 minutes.
Train measures
- Sprinter 8600 Gouda - Alphen a/d Rijn is cancelled between Boskoop and Gouda
-
Update
Between Boskoop and Gouda no trains are running due to a signal and level crossing failure.
This will take until approximately 11:30 PM hours.Advice
Passengers between Alphen a/d Rijn and Gouda travel via Woerden. The extra travel time is up to 15 minutes.
Train measures
- Sprinter 8600 Gouda - Alphen a/d Rijn is cancelled between Boskoop and Gouda
-
Update
Between Boskoop and Gouda no trains are running due to a signal and level crossing failure.
This will take until approximately 11:30 PM hours.Advice
Passengers between Alphen a/d Rijn and Gouda travel via Woerden. The extra travel time is up to 15 minutes.
-
Update
Between Boskoop and Gouda no trains are running due to a signal and level crossing failure.
This will take until approximately 11:30 PM hours. -
Disruption
Between Alphen a/d Rijn and Gouda there is a service disruption due to a signal and level crossing failure.
Updates will follow as more information becomes available.
More about this disruption
Statistics
This disruption started at 9:30 PM on April 28, 2021 and took 1 hour, 39 minutes in total.
For statistics, this disruption is caused due to a signal and level crossing failure.
Operators
This disruption affects trains operated by R-net.
Got delayed due to this disruption? You may be reimbursed.