Over-running engineering works: Leiden-Den Haag C (5 May 2021)

  1. Disruption resolved Last update

    Between Leiden Centraal and Den Haag Centraal the train traffic is fully resumed.

  2. Disruption

    Between Leiden Centraal and Den Haag Centraal fewer intercities are running due to over-running engineering works.
    The extra travel time may be up to 15 minutes.
    This will take until approximately 6:15 AM hours.

More about this disruption

Statistics

This disruption started at 5:34 AM on May 5, 2021 and took 10 minutes in total.

For statistics, this disruption is caused due to over-running engineering works.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.