Large signalling and points failure: Haarlem (31 May 2021)
-
Disruption resolved Last update
From and to Haarlem the train traffic is fully resumed.
-
Update
From and to Haarlem there are fewer trains running due to a large signalling and points failure.
The extra travel time may be up to 30 minutes.
Service is normal around 9:30 PM hours. -
Update
From and to Haarlem there are fewer trains running due to a large signalling and points failure.
From and to Zaandam there are fewer trains running due to a large signalling and points failure.
The extra travel time may be up to 30 minutes.
Service is normal around 8:00 PM hours. -
Update
From and to Haarlem far fewer trains are running due to a large signalling and points failure.
From and to Zaandam far fewer trains are running due to a large signalling and points failure.
The extra travel time may be up to 60 minutes.
Service is normal around 8:00 PM hours. -
Update
From and to Haarlem no trains are running due to a large signalling and points failure.
From and to Zaandam no trains are running due to a large signalling and points failure.
The extra travel time may be up to 120 minutes.
This will take until at least 5:00 PM hours. -
Update
From and to Zaandam no trains are running due to a large signalling and points failure.
From and to Haarlem no trains are running due to a large signalling and points failure.
The extra travel time may be up to 120 minutes.
This will take until at least 4:30 PM hours. -
Update
From and to Haarlem no trains are running due to a large signalling and points failure.
From and to Zaandam no trains are running due to a large signalling and points failure.
The extra travel time may be up to 120 minutes.
This will take until at least 4:30 PM hours. -
Update
From and to Alkmaar no trains are running due to a large signalling and points failure.
This will take until at least 4:30 PM hours. -
Disruption
From and to Alkmaar no trains are running due to a large signalling and points failure.
Updates will follow as more information becomes available.
More about this disruption
Statistics
This disruption started at 2:30 PM on May 31, 2021 and took 7 hours, 2 minutes in total.
For statistics, this disruption is caused due to a large signalling and points failure.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.