Collision: Maastricht-Randwijck (27 August 2021)
-
Disruption resolved Last update
Between Maastricht and Maastricht Randwyck the train traffic is fully resumed.
-
Delays decreasing
Between Maastricht and Maastricht Randwyck the restrictions are resolved.
Delays are decreasing.
Service is normal around 6:00 PM hours.Advice
Local buses are still running between Maastricht, Maastricht Randwyck, Eijsden and Visé.
-
Update
Between Maastricht and Maastricht Randwyck no trains are running due to a collision.
The extra travel time is more than 30 minutes.
This will take until approximately 6:00 PM hours.Advice
Local buses are running between Maastricht, Maastricht Randwyck, Eijsden and Visé.
Train measures
- Stoptrein 32000 Randwyck - Heerlen - Kerkrade C. is cancelled between Maastricht and Maastricht Randwyck
- Stoptrein 32400 Roermond - Maastricht - Randwyck is cancelled between Maastricht and Maastricht Randwyck
-
Update
Between Maastricht and Maastricht Randwyck no trains are running due to a collision.
The extra travel time is more than 60 minutes.
This will take until approximately 6:00 PM hours.Advice
Local buses are running between Maastricht, Maastricht Randwyck, Eijsden and Visé.
Train measures
- Stoptrein 32000 Randwyck - Heerlen - Kerkrade C. is cancelled between Maastricht and Maastricht Randwyck
- Stoptrein 32400 Roermond - Maastricht - Randwyck is cancelled between Maastricht and Maastricht Randwyck
-
Update
Between Maastricht and Maastricht Randwyck no trains are running due to a collision.
The extra travel time is more than 60 minutes.
This will take until approximately 6:00 PM hours.Train measures
- Stoptrein 32000 Randwyck - Heerlen - Kerkrade C. is cancelled between Maastricht and Maastricht Randwyck
- Stoptrein 32400 Roermond - Maastricht - Randwyck is cancelled between Maastricht and Maastricht Randwyck
-
Update
Between Maastricht and Maastricht Randwyck no trains are running due to a collision.
The extra travel time is more than 60 minutes.
This will take until approximately 6:00 PM hours. -
Disruption
Between Maastricht and Maastricht Randwyck no trains are running due to a collision.
This will take until approximately 6:00 PM hours.
More about this disruption
Statistics
This disruption started at 2:45 PM on August 27, 2021 and took 3 hours, 11 minutes in total.
For statistics, this disruption is caused due to a collision.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by Arriva and NMBS.
Got delayed due to this disruption? You may be reimbursed.