defecte bovenleiding

Damaged overhead wires: Breda-'s-Hertogenbosch (27 August 2021)

  1. Disruption resolved Last update

    Between Tilburg and 's-Hertogenbosch the train traffic is fully resumed.

  2. Delays decreasing

    Between Tilburg and 's-Hertogenbosch the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 2:00 AM hours.

  3. Update

    Between Tilburg and 's-Hertogenbosch far fewer trains are running due to damaged overhead wires.
    This will take until approximately 1:30 AM on Saturday, August 28, 2021.

    Train measures

    • Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between 's-Hertogenbosch and Tilburg
    • Sprinter 6600 Dordrecht - Breda - 's-Hertogenbosch - Arnhem C. runs only once per hour between 's-Hertogenbosch and Tilburg
  4. Update

    Between Tilburg and 's-Hertogenbosch far fewer trains are running due to damaged overhead wires.
    This will take until approximately 1:30 AM on Saturday, August 28, 2021.

    Train measures

    • Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between 's-Hertogenbosch and Breda
    • Sprinter 6600 Dordrecht - Breda - 's-Hertogenbosch - Arnhem C. runs only once per hour between 's-Hertogenbosch and Breda
  5. Update

    Between Tilburg and 's-Hertogenbosch far fewer trains are running due to damaged overhead wires.
    This will take until approximately 9:30 PM hours.

    Train measures

    • Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between 's-Hertogenbosch and Breda
    • Sprinter 6600 Dordrecht - Breda - 's-Hertogenbosch - Arnhem C. runs only once per hour between 's-Hertogenbosch and Breda
  6. Update

    Between Breda and 's-Hertogenbosch far fewer trains are running due to damaged overhead wires.
    This will take until approximately 9:30 PM hours.

    Train measures

    • Intercity 3600 Zwolle - Deventer - Nijmegen - Roosendaal is cancelled between 's-Hertogenbosch and Breda
    • Sprinter 6600 Dordrecht - Breda - 's-Hertogenbosch - Arnhem C. runs only once per hour between 's-Hertogenbosch and Breda
  7. Update

    Between Breda and 's-Hertogenbosch far fewer trains are running due to damaged overhead wires.
    This will take until approximately 9:30 PM hours.

  8. Update

    Between 's-Hertogenbosch and Tilburg no trains are running due to damaged overhead wires.
    This will take until approximately 9:30 PM hours.

  9. Disruption

    Between Tilburg and 's-Hertogenbosch no trains are running due to damaged overhead wires.
    This will take until approximately 9:30 PM hours.

More about this disruption

Statistics

This disruption started at 4:58 PM on August 27, 2021 and took 9 hours in total.

For statistics, this disruption is caused due to damaged overhead wires.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.