sein- en overwegstoring

Signal and level crossing failure: Utrecht-Rhenen (3 December 2021)

  1. Disruption resolved Last update

    Between Veenendaal Centrum and Rhenen the train traffic is fully resumed.

  2. Delays decreasing

    Between Veenendaal Centrum and Rhenen the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 7:00 AM hours.

  3. Update

    Between Veenendaal Centrum and Rhenen no trains are running due to a signal and level crossing failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 8:45 AM hours.

    Train measures

    • Sprinter 7400 Uitgeest - Amsterdam C. - Utrecht C. - Rhenen is cancelled between Veenendaal Centrum and Rhenen
  4. Update

    Between Veenendaal Centrum and Rhenen no trains are running due to a signal and level crossing failure.
    The extra travel time is more than 60 minutes.
    It is not known yet how long this will take.

    Train measures

    • Sprinter 7400 Uitgeest - Amsterdam C. - Utrecht C. - Rhenen is cancelled between Veenendaal Centrum and Rhenen
  5. Disruption

    Between Veenendaal Centrum and Rhenen there is a service disruption due to a signal and level crossing failure.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 5:28 AM on December 3, 2021 and took 1 hour, 40 minutes in total.

For statistics, this disruption is caused due to a signal and level crossing failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights