Points failure: Den Haag-Rotterdam (21 December 2021)
-
Disruption resolved Last update
Between Den Haag HS and Schiedam Centrum the train traffic is fully resumed.
-
Delays decreasing
Between Den Haag HS and Schiedam Centrum the restrictions are resolved.
Delays are decreasing.
Service is normal around 9:15 AM hours. -
Delays decreasing
Between Den Haag HS and Schiedam Centrum the restrictions are resolved.
Delays are decreasing.
Service is normal around 9:15 AM hours.Advice
Local buses are still running between Delft and Delft Campus.
-
Update
Between Den Haag HS and Schiedam Centrum there are fewer trains running due to a points failure.
The extra travel time may be up to 15 minutes.
This will take until approximately 9:00 AM hours.Advice
Local buses are running between Delft and Delft Campus.
Train measures
- Intercity 1100 Den Haag C. - Rotterdam C. - Eindhoven C. is cancelled between Den Haag Centraal and Rotterdam Centraal
- Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag HS and Schiedam Centrum
- Sprinter 5100 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag HS and Schiedam Centrum
-
Update
Between Den Haag HS and Schiedam Centrum there are fewer trains running due to a points failure.
The extra travel time may be up to 15 minutes.
This will take until approximately 9:00 AM hours.Train measures
- Intercity 1100 Den Haag C. - Rotterdam C. - Eindhoven C. is cancelled between Den Haag Centraal and Rotterdam Centraal
- Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag HS and Schiedam Centrum
- Sprinter 5100 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag HS and Schiedam Centrum
-
Update
Between Den Haag HS and Schiedam Centrum there are fewer trains running due to a points failure.
The extra travel time may be up to 15 minutes.
This will take until approximately 9:00 AM hours. -
Disruption
Between Den Haag HS and Delft far fewer trains are running due to a points failure.
This will take until approximately 9:00 AM hours.
More about this disruption
Statistics
This disruption started at 6:13 AM on December 21, 2021 and took 3 hours, 2 minutes in total.
For statistics, this disruption is caused due to a points failure.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.