wisselstoring

Points failure: Amersfoort-Ede-Wageningen (22 December 2021)

  1. Disruption resolved Last update

    Between Amersfoort Centraal and Barneveld Centrum the train traffic is fully resumed.

  2. Delays decreasing

    Between Amersfoort Centraal and Barneveld Centrum the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 2:30 PM hours.

    Advice

    Local buses are still running between Barneveld Centrum, Barneveld Noord, Hoevelaken and Amersfoort Centraal.

  3. Update

    Between Amersfoort Centraal and Barneveld Centrum no trains are running due to a points failure.
    This will take until approximately 2:30 PM hours.

    Advice

    Local buses are running between Barneveld Centrum, Barneveld Noord, Hoevelaken and Amersfoort Centraal.

    Train measures

    • Stoptrein 31300 Amersfoort C. - Ede-Wageningen is cancelled between Amersfoort Centraal and Barneveld Centrum
    • Stoptrein 31400 Amersfoort C. - Barneveld Z. is cancelled between Amersfoort Centraal and Barneveld Centrum
  4. Update

    Between Amersfoort Centraal and Barneveld Centrum no trains are running due to a points failure.
    This will take until approximately 3:30 PM hours.

    Advice

    Local buses are running between Barneveld Centrum, Barneveld Noord, Hoevelaken and Amersfoort Centraal.

    Train measures

    • Stoptrein 31300 Amersfoort C. - Ede-Wageningen is cancelled between Amersfoort Centraal and Barneveld Centrum
    • Stoptrein 31400 Amersfoort C. - Barneveld Z. is cancelled between Amersfoort Centraal and Barneveld Centrum
  5. Update

    Between Amersfoort Centraal and Barneveld Centrum no trains are running due to a points failure.
    This will take until approximately 3:00 PM hours.

    Advice

    Local buses are running between Barneveld Centrum, Barneveld Noord, Hoevelaken and Amersfoort Centraal.

    Train measures

    • Stoptrein 31300 Amersfoort C. - Ede-Wageningen is cancelled between Amersfoort Centraal and Barneveld Centrum
    • Stoptrein 31400 Amersfoort C. - Barneveld Z. is cancelled between Amersfoort Centraal and Barneveld Centrum
  6. Update

    Between Amersfoort Centraal and Barneveld Centrum no trains are running due to a points failure.
    This will take until approximately 3:00 PM hours.

    Train measures

    • Stoptrein 31300 Amersfoort C. - Ede-Wageningen is cancelled between Amersfoort Centraal and Barneveld Centrum
    • Stoptrein 31400 Amersfoort C. - Barneveld Z. is cancelled between Amersfoort Centraal and Barneveld Centrum
  7. Update

    Between Amersfoort Centraal and Barneveld Centrum no trains are running due to a points failure.
    This will take until approximately 3:00 PM hours.

    Train measures

    • Stoptrein 31300 Amersfoort C. - Ede-Wageningen is cancelled between Amersfoort Centraal and Barneveld Centrum
    • Stoptrein 31400 Amersfoort C. - Barneveld Z. is cancelled between Amersfoort Centraal and Barneveld Zuid
  8. Update

    Between Amersfoort Centraal and Barneveld Centrum no trains are running due to a points failure.
    This will take until approximately 3:00 PM hours.

  9. Update

    Between Hoevelaken and Barneveld Centrum no trains are running due to a points failure.
    This will take until approximately 3:00 PM hours.

  10. Update

    Between Hoevelaken and Barneveld Centrum no trains are running due to a points failure.
    Updates will follow as more information becomes available.

  11. Disruption

    Between Hoevelaken and Barneveld Centrum there is a service disruption due to a points failure.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 12:29 PM on December 22, 2021 and took 1 hour, 55 minutes in total.

For statistics, this disruption is caused due to a points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by Connexxion.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights