Damaged overhead wires: Den Haag-Rotterdam; Rotterdam-Dordrecht (31 January 2022)
-
Disruption resolved Last update
Between Rotterdam Centraal and Dordrecht the train traffic is fully resumed.
Between Den Haag Centraal and Rotterdam Centraal the train traffic is fully resumed. -
Delays decreasing
Between Den Haag Centraal and Rotterdam Centraal the restrictions are resolved.
Between Rotterdam Centraal and Dordrecht the restrictions are resolved.
Delays are decreasing.
Service is normal around 1:30 PM hours. -
Update
Between Den Haag Centraal and Rotterdam Centraal fewer Sprinter trains are running due to damaged overhead wires.
Between Rotterdam Centraal and Dordrecht fewer Sprinter trains are running due to damaged overhead wires.
The extra travel time may be up to 15 minutes.
This will take until approximately 2:00 PM hours.Train measures
- Sprinter 5100 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag Centraal and Dordrecht
-
Update
Between Rotterdam Centraal and Dordrecht fewer Sprinter trains are running due to damaged overhead wires.
Between Den Haag Centraal and Rotterdam Centraal fewer Sprinter trains are running due to damaged overhead wires.
The extra travel time may be up to 15 minutes.
This will take until approximately 2:30 PM hours.Train measures
- Sprinter 5100 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag Centraal and Dordrecht
-
Update
Between Rotterdam Centraal and Dordrecht fewer Sprinter trains are running due to damaged overhead wires.
Between Den Haag Centraal and Rotterdam Centraal fewer Sprinter trains are running due to damaged overhead wires.
The extra travel time may be up to 15 minutes.
This will take until approximately 3:15 PM hours. -
Disruption
Between Den Haag Centraal and Rotterdam Centraal fewer Sprinter trains are running due to damaged overhead wires.
Between Rotterdam Centraal and Dordrecht fewer Sprinter trains are running due to damaged overhead wires.
The extra travel time may be up to 15 minutes.
This will take until approximately 3:15 PM hours.
More about this disruption
Statistics
This disruption started at 12:43 PM on January 31, 2022 and took 43 minutes in total.
For statistics, this disruption is caused due to damaged overhead wires.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.