Engineering works: Utrecht-Hilversum (13 February 2022)
-
Disruption resolved Last update
Between Utrecht Centraal and Hilversum the train traffic is fully resumed.
-
Delays decreasing
Between Utrecht Centraal and Hilversum the restrictions are resolved.
Delays are decreasing.
Service is normal around 11:10 AM hours. -
Disruption
Between Utrecht Centraal and Hilversum fewer Sprinter trains are running due to engineering works.
This will take at least until 8:00 PM hours.
More about this disruption
Statistics
This disruption started at 9:47 AM on February 13, 2022 and took 1 hour, 22 minutes in total.
For statistics, this disruption is caused due to engineering works.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.