Signal failure: Amsterdam-Utrecht; Amsterdam-Gouda (2 March 2022)

  1. Disruption resolved Last update

    Between Amsterdam Centraal and Utrecht Centraal the train traffic is fully resumed.
    Between Breukelen and Gouda Goverwelle the train traffic is fully resumed.

  2. Delays decreasing

    Between Amsterdam Centraal and Utrecht Centraal the restrictions are resolved.
    Between Breukelen and Gouda Goverwelle the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 12:00 PM hours.

    Advice

    Use the Amsterdam metro system between Amsterdam Centraal, Amsterdam Amstel, Duivendrecht, Amsterdam Bijlmer ArenA and Amsterdam Holendrecht.
    Local buses are still running between Utrecht Centraal, Utrecht Zuilen, Maarssen, Breukelen, Abcoude and Amsterdam Holendrecht.

  3. Delays decreasing

    Between Amsterdam Centraal and Utrecht Centraal the restrictions are resolved.
    Between Breukelen and Gouda Goverwelle the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 12:30 PM hours.

    Advice

    Use the Amsterdam metro system between Amsterdam Centraal, Amsterdam Amstel, Duivendrecht, Amsterdam Bijlmer ArenA and Amsterdam Holendrecht.
    Local buses are still running between Utrecht Centraal, Utrecht Zuilen, Maarssen, Breukelen, Abcoude and Amsterdam Holendrecht.

  4. Update

    Between Amsterdam Centraal and Utrecht Centraal far fewer trains are running due to a signal failure.
    Between Breukelen and Gouda Goverwelle no Sprinters are running due to a signal failure.
    This will take until approximately 12:30 PM hours.

    Advice

    Local buses are running between Utrecht Centraal, Utrecht Zuilen, Maarssen, Breukelen, Abcoude and Amsterdam Holendrecht.
    Use the Amsterdam metro system between Amsterdam Centraal, Amsterdam Amstel, Duivendrecht, Amsterdam Bijlmer ArenA and Amsterdam Holendrecht.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven C. - Maastricht is cancelled between Amsterdam Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Amsterdam Centraal and Gouda Goverwelle
    • Sprinter 7300 Breukelen - Utrecht C. - Rhenen is cancelled between Breukelen and Utrecht Centraal
    • Sprinter 7400 Uitgeest - Amsterdam C. - Utrecht C. - Driebergen-Zeist is cancelled between Amsterdam Centraal and Driebergen-Zeist
  5. Update

    Between Breukelen and Gouda Goverwelle no Sprinters are running due to a signal failure.
    Between Amsterdam Centraal and Utrecht Centraal far fewer trains are running due to a signal failure.
    This will take until approximately 12:30 PM hours.

    Advice

    Use the Amsterdam metro system between Amsterdam Centraal, Amsterdam Amstel, Duivendrecht, Amsterdam Bijlmer ArenA and Amsterdam Holendrecht.
    Local buses are running between Utrecht Centraal, Utrecht Zuilen, Maarssen, Breukelen, Abcoude and Amsterdam Holendrecht.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven C. - Maastricht is cancelled between Amsterdam Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Amsterdam Centraal and Gouda Goverwelle
    • Sprinter 7300 Breukelen - Utrecht C. - Rhenen keeps running normally between Breukelen and Utrecht Centraal
    • Sprinter 7400 Uitgeest - Amsterdam C. - Utrecht C. - Driebergen-Zeist is cancelled between Amsterdam Centraal and Driebergen-Zeist
  6. Update

    Between Breukelen and Gouda Goverwelle no Sprinters are running due to a signal failure.
    Between Amsterdam Centraal and Utrecht Centraal far fewer trains are running due to a signal failure.
    This will take until approximately 9:30 AM hours.

    Advice

    Local buses are running between Utrecht Centraal, Utrecht Zuilen, Maarssen, Breukelen, Abcoude and Amsterdam Holendrecht.
    Use the Amsterdam metro system between Amsterdam Centraal, Amsterdam Amstel, Duivendrecht, Amsterdam Bijlmer ArenA and Amsterdam Holendrecht.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven C. - Maastricht is cancelled between Amsterdam Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Amsterdam Centraal and Gouda Goverwelle
    • Sprinter 7300 Breukelen - Utrecht C. - Rhenen keeps running normally between Breukelen and Utrecht Centraal
    • Sprinter 7400 Uitgeest - Amsterdam C. - Utrecht C. - Driebergen-Zeist is cancelled between Amsterdam Centraal and Driebergen-Zeist
  7. Update

    Between Breukelen and Gouda Goverwelle no Sprinters are running due to a signal failure.
    Between Amsterdam Centraal and Utrecht Centraal far fewer trains are running due to a signal failure.
    This will take until approximately 9:30 AM hours.

    Advice

    Use the Amsterdam metro system between Amsterdam Centraal, Amsterdam Amstel, Duivendrecht, Amsterdam Bijlmer ArenA and Amsterdam Holendrecht.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven C. - Maastricht is cancelled between Amsterdam Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Amsterdam Centraal and Gouda Goverwelle
    • Sprinter 7300 Breukelen - Utrecht C. - Rhenen keeps running normally between Breukelen and Utrecht Centraal
    • Sprinter 7400 Uitgeest - Amsterdam C. - Utrecht C. - Driebergen-Zeist is cancelled between Amsterdam Centraal and Driebergen-Zeist
  8. Update

    Between Amsterdam Centraal and Utrecht Centraal far fewer trains are running due to a signal failure.
    Between Breukelen and Gouda Goverwelle no Sprinters are running due to a signal failure.
    This will take until approximately 9:30 AM hours.

    Advice

    Use the Amsterdam metro system between Amsterdam Centraal, Amsterdam Amstel, Duivendrecht, Amsterdam Bijlmer ArenA and Amsterdam Holendrecht.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven C. - Maastricht is cancelled between Amsterdam Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Amsterdam Centraal and Gouda Goverwelle
    • Sprinter 7300 Breukelen - Utrecht C. - Rhenen is cancelled between Breukelen and Utrecht Centraal
    • Sprinter 7400 Uitgeest - Amsterdam C. - Utrecht C. - Driebergen-Zeist is cancelled between Amsterdam Centraal and Driebergen-Zeist
  9. Update

    Between Amsterdam Centraal and Utrecht Centraal far fewer trains are running due to a signal failure.
    Between Breukelen and Gouda Goverwelle no Sprinters are running due to a signal failure.
    This will take until approximately 9:30 AM hours.

    Advice

    Use the Amsterdam metro system between Amsterdam Centraal, Amsterdam Amstel, Duivendrecht, Amsterdam Bijlmer ArenA and Amsterdam Holendrecht.
    Minibuses are available between Bunnik and Driebergen-Zeist.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven C. - Maastricht is cancelled between Amsterdam Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Amsterdam Centraal and Gouda Goverwelle
    • Sprinter 7300 Breukelen - Utrecht C. - Rhenen is cancelled between Breukelen and Utrecht Centraal
    • Sprinter 7400 Uitgeest - Amsterdam C. - Utrecht C. - Driebergen-Zeist is cancelled between Amsterdam Centraal and Driebergen-Zeist
  10. Update

    Between Breukelen and Gouda Goverwelle no Sprinters are running due to a signal failure.
    Between Amsterdam Centraal and Utrecht Centraal far fewer trains are running due to a signal failure.
    This will take until approximately 9:30 AM hours.

    Advice

    Use the Amsterdam metro system between Amsterdam Centraal, Amsterdam Amstel, Duivendrecht, Amsterdam Bijlmer ArenA and Amsterdam Holendrecht.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven C. - Maastricht is cancelled between Amsterdam Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Amsterdam Centraal and Gouda Goverwelle
    • Sprinter 7300 Breukelen - Utrecht C. - Rhenen is cancelled between Breukelen and Utrecht Centraal
    • Sprinter 7400 Uitgeest - Amsterdam C. - Utrecht C. - Driebergen-Zeist is cancelled between Amsterdam Centraal and Driebergen-Zeist
  11. Update

    Between Amsterdam Centraal and Utrecht Centraal far fewer trains are running due to a signal failure.
    Between Breukelen and Gouda Goverwelle no Sprinters are running due to a signal failure.
    This will take until approximately 7:00 AM hours.

    Advice

    Use the Amsterdam metro system between Amsterdam Centraal, Amsterdam Amstel, Duivendrecht, Amsterdam Bijlmer ArenA and Amsterdam Holendrecht.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven C. - Maastricht is cancelled between Amsterdam Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Amsterdam Centraal and Gouda Goverwelle
    • Sprinter 7300 Breukelen - Utrecht C. - Rhenen is cancelled between Breukelen and Utrecht Centraal
    • Sprinter 7400 Uitgeest - Amsterdam C. - Utrecht C. - Driebergen-Zeist is cancelled between Amsterdam Centraal and Driebergen-Zeist
  12. Update

    Between Breukelen and Gouda Goverwelle no Sprinters are running due to a signal failure.
    Between Amsterdam Centraal and Utrecht Centraal far fewer trains are running due to a signal failure.
    This will take until approximately 7:00 AM hours.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven C. - Maastricht is cancelled between Amsterdam Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Amsterdam Centraal and Gouda Goverwelle
    • Sprinter 7300 Breukelen - Utrecht C. - Rhenen is cancelled between Breukelen and Utrecht Centraal
    • Sprinter 7400 Uitgeest - Amsterdam C. - Utrecht C. - Driebergen-Zeist is cancelled between Amsterdam Centraal and Driebergen-Zeist
  13. Update

    Between Amsterdam Centraal and Utrecht Centraal far fewer trains are running due to a signal failure.
    Between Breukelen and Gouda Goverwelle no Sprinters are running due to a signal failure.
    This will take until approximately 7:00 AM hours.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven C. - Maastricht is cancelled between Amsterdam Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Amsterdam Centraal and Gouda Goverwelle
    • Sprinter 7300 Breukelen - Utrecht C. - Rhenen is cancelled between Breukelen and Utrecht Centraal
    • Sprinter 7400 Uitgeest - Amsterdam C. - Utrecht C. - Driebergen-Zeist is cancelled between Amsterdam Centraal and Driebergen-Zeist
  14. Disruption

    Between Breukelen and Gouda Goverwelle no Sprinters are running due to a signal failure.
    Between Amsterdam Centraal and Utrecht Centraal far fewer trains are running due to a signal failure.
    Updates will follow as more information becomes available.

    Train measures

    • Intercity 800 Alkmaar - Utrecht C. - Eindhoven C. - Maastricht is cancelled between Amsterdam Centraal and Utrecht Centraal
    • Sprinter 4000 Rotterdam C. - Woerden - Amsterdam C. - Uitgeest is cancelled between Amsterdam Centraal and Gouda Goverwelle
    • Sprinter 7300 Breukelen - Utrecht C. - Rhenen is cancelled between Breukelen and Utrecht Centraal
    • Sprinter 7400 Uitgeest - Amsterdam C. - Utrecht C. - Driebergen-Zeist is cancelled between Amsterdam Centraal and Driebergen-Zeist

More about this disruption

Statistics

This disruption started at 5:09 AM on March 2, 2022 and took 6 hours, 55 minutes in total.

For statistics, this disruption is caused due to a signal failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS and NS International.