Points failure: Den Haag-Gouda Goverwelle (20 May 2022)
-
Disruption resolved Last update
Between Gouda and Gouda Goverwelle the train traffic is fully resumed.
-
Delays decreasing
Between Gouda and Gouda Goverwelle the restrictions are resolved.
Delays are decreasing.
Service is normal around 9:00 PM hours. -
Update
Between Gouda and Gouda Goverwelle fewer Sprinter trains are running due to a points failure.
This will take until approximately 9:00 PM hours.Train measures
- Intercity 2000 Den Haag C. - Utrecht C. - Amersfoort C. keeps running normally between Den Haag Centraal and Utrecht Centraal
- Sprinter 6800 Den Haag C. - Goverwelle is cancelled between Gouda and Gouda Goverwelle
-
Update
Between Gouda and Gouda Goverwelle fewer Sprinter trains are running due to a points failure.
This will take until approximately 9:00 PM hours.Advice
Between 4:00 PM and 6:30 PM, there will be fewer sprinters running between Rotterdam and Gouda Goverwelle.
Train measures
- Intercity 2000 Den Haag C. - Utrecht C. - Amersfoort C. keeps running normally between Den Haag Centraal and Utrecht Centraal
- Sprinter 6800 Den Haag C. - Goverwelle is cancelled between Gouda and Gouda Goverwelle
-
Disruption
Between Gouda and Gouda Goverwelle fewer Sprinter trains are running due to a points failure.
This will take until approximately 9:00 PM hours.Train measures
- Intercity 2000 Den Haag C. - Utrecht C. - Amersfoort C. keeps running normally between Den Haag Centraal and Utrecht Centraal
- Sprinter 6800 Den Haag C. - Goverwelle is cancelled between Gouda and Gouda Goverwelle
More about this disruption
Statistics
This disruption started at 10:03 AM on May 20, 2022 and took 10 hours, 56 minutes in total.
For statistics, this disruption is caused due to a points failure.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.