Over-running engineering works: Heerlen-Kerkrade; Heerlen-Aachen Hbf (11 July 2022)
-
Disruption resolved Last update
Between Heerlen and Herzogenrath the train traffic is fully resumed.
Between Heerlen and Landgraaf the train traffic is fully resumed. -
Delays decreasing
Between Heerlen and Herzogenrath the restrictions are resolved.
Between Heerlen and Landgraaf the restrictions are resolved.
Delays are decreasing.
Service is normal around 7:15 AM hours. -
Update
Between Heerlen and Herzogenrath no trains are running due to over-running engineering works.
Between Heerlen and Landgraaf no trains are running due to over-running engineering works.
The extra travel time is more than 60 minutes.
This will take until approximately 7:15 AM hours.Train measures
- Stoptrein 32500 Sittard - Heerlen - Kerkrade C. is cancelled between Heerlen and Landgraaf
-
Update
Between Heerlen and Herzogenrath no trains are running due to over-running engineering works.
Between Heerlen and Landgraaf no trains are running due to over-running engineering works.
The extra travel time is more than 60 minutes.
This will take until approximately 7:00 AM hours.Train measures
- Stoptrein 32500 Sittard - Heerlen - Kerkrade C. is cancelled between Heerlen and Landgraaf
-
Disruption
Between Heerlen and Herzogenrath no trains are running due to over-running engineering works.
Between Heerlen and Landgraaf no trains are running due to over-running engineering works.
The extra travel time is more than 60 minutes.
This will take until approximately 7:00 AM hours.
More about this disruption
Statistics
This disruption started at 5:44 AM on July 11, 2022 and took 1 hour, 31 minutes in total.
For statistics, this disruption is caused due to over-running engineering works.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by Arriva.
Got delayed due to this disruption? You may be reimbursed.