Collision: Almere-Zwolle (21 August 2022)
-
Disruption resolved Last update
Between Lelystad Centrum and Kampen Zuid the train traffic is fully resumed.
-
Delays decreasing
Between Lelystad Centrum and Kampen Zuid the restrictions are resolved.
Delays are decreasing.
Service is normal around 11:55 PM hours. -
Update
Between Lelystad Centrum and Kampen Zuid no trains are running due to a collision.
This will take until approximately 1:15 AM on Monday, August 22, 2022.Train measures
- Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Lelystad Centrum and Zwolle
- Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Lelystad Centrum and Zwolle
- Sprinter 14600 Amsterdam C. - Lelystad C. - Zwolle is cancelled between Lelystad Centrum and Kampen Zuid
-
Update
Between Lelystad Centrum and Kampen Zuid no trains are running due to a collision.
This will take until approximately 2:30 AM on Monday, August 22, 2022.Train measures
- Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Lelystad Centrum and Zwolle
- Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Lelystad Centrum and Zwolle
- Sprinter 14600 Amsterdam C. - Lelystad C. - Zwolle is cancelled between Lelystad Centrum and Kampen Zuid
-
Update
Between Lelystad Centrum and Dronten no trains are running due to a collision.
This will take until approximately 2:30 AM on Monday, August 22, 2022.Train measures
- Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Lelystad Centrum and Zwolle
- Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Lelystad Centrum and Zwolle
- Sprinter 14600 Amsterdam C. - Lelystad C. - Zwolle is cancelled between Lelystad Centrum and Dronten
-
Disruption
Between Lelystad Centrum and Zwolle no trains are running due to a collision.
This will take until approximately 2:30 AM on Monday, August 22, 2022.
More about this disruption
Statistics
This disruption started at 11:04 PM on August 21, 2022 and took 54 minutes in total.
For statistics, this disruption is caused due to a collision.
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.