Signalling and points failure: Leiden-Duivendrecht-Lelystad (31 October 2022)
-
Disruption resolved Last update
Between Leiden Centraal and Almere Centrum the train traffic is fully resumed.
-
Update
Between Leiden Centraal and Almere Centrum fewer intercities are running due to a signalling and points failure.
The extra travel time may be up to 15 minutes.
This will take until approximately 7:30 PM hours.Train measures
- Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Almere Centrum and Leiden Centraal
-
Update
Between Almere Centrum and Leiden Centraal no intercities are running due to a signalling and points failure.
The extra travel time may be up to 30 minutes.
This will take until approximately 5:00 PM hours.Train measures
- Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Almere Centrum and Den Haag Centraal
- Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Almere Centrum and Den Haag Centraal
- Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Almere Centrum and Leiden Centraal
-
Update
Between Almere Centrum and Leiden Centraal no intercities are running due to a signalling and points failure.
The extra travel time may be up to 30 minutes.
This will take until approximately 4:30 PM hours.Train measures
- Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Almere Centrum and Den Haag Centraal
- Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Almere Centrum and Den Haag Centraal
- Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Almere Centrum and Leiden Centraal
-
Update
Between Almere Centrum and Leiden Centraal no intercities are running due to a signalling and points failure.
The extra travel time may be up to 30 minutes.
This will take until approximately 4:00 PM hours.Train measures
- Intercity 700 Den Haag C. - Schiphol Airport - Lelystad C. - Groningen is cancelled between Almere Centrum and Den Haag Centraal
- Intercity 1800 Den Haag C. - Schiphol Airport - Lelystad C. - Leeuwarden is cancelled between Almere Centrum and Den Haag Centraal
- Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Almere Centrum and Leiden Centraal
-
Update
Between Almere Centrum and Leiden Centraal no intercities are running due to a signalling and points failure.
The extra travel time may be up to 30 minutes.
This will take until approximately 4:00 PM hours.Train measures
- Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Almere Centrum and Leiden Centraal
-
Update
Between Almere Centrum and Leiden Centraal no intercities are running due to a signalling and points failure.
The extra travel time may be up to 30 minutes.
This will take until approximately 2:00 PM hours.Train measures
- Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Almere Centrum and Leiden Centraal
-
Update
Between Almere Centrum and Leiden Centraal no intercities are running due to a signalling and points failure.
The extra travel time may be up to 30 minutes.
This will take at least until 12:30 PM hours.Train measures
- Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Almere Centrum and Leiden Centraal
-
Update
Between Almere Centrum and Leiden Centraal no intercities are running due to a signalling and points failure.
The extra travel time may be up to 30 minutes.
This will take the rest of the day.Train measures
- Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Almere Centrum and Leiden Centraal
-
Update
Between Almere Centrum and Leiden Centraal no intercities are running due to a signalling and points failure.
The extra travel time may be up to 30 minutes.
This will take until approximately 11:30 AM hours.Train measures
- Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Almere Centrum and Leiden Centraal
-
Update
Between Almere Centrum and Leiden Centraal no intercities are running due to a signalling and points failure.
The extra travel time may be up to 30 minutes.
This will take until approximately 11:30 AM hours. -
Update
Between Schiphol Airport and Duivendrecht there is a service disruption due to a signalling and points failure.
This will take until approximately 11:30 AM hours. -
Disruption
Between Schiphol Airport and Duivendrecht there is a service disruption due to a signalling and points failure.
This will take until approximately 9:30 AM hours.
More about this disruption
Statistics
This disruption started at 6:29 AM on October 31, 2022 and took 13 hours, 9 minutes in total.
For statistics, this disruption is caused due to a signalling and points failure.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.