Repair works: Roosendaal-Vlissingen (28 December 2022)
-
Disruption resolved Last update
Between Bergen op Zoom and Kruiningen-Yerseke the train traffic is fully resumed.
-
Delays decreasing
Between Bergen op Zoom and Kruiningen-Yerseke the restrictions are resolved.
Delays are decreasing.
Service is normal around 8:00 AM hours.Advice
Local buses are still running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.
-
Update
Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to repair works.
The extra travel time is more than 60 minutes.
This will take until approximately 8:00 AM hours.Advice
Local buses are running between Bergen op Zoom, Rilland-Bath, Krabbendijke and Kruiningen-Yerseke.
Train measures
- Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Bergen op Zoom and Kruiningen-Yerseke
- Sprinter 6100 Roosendaal - Vlissingen is cancelled between Roosendaal and Kruiningen-Yerseke
-
Update
Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to repair works.
The extra travel time is more than 60 minutes.
This will take until approximately 8:00 AM hours.Train measures
- Sprinter 6100 Roosendaal - Vlissingen is cancelled between Roosendaal and Kruiningen-Yerseke
-
Update
Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to repair works.
The extra travel time is more than 60 minutes.
This will take until approximately 8:15 AM hours.Train measures
- Sprinter 6100 Roosendaal - Vlissingen is cancelled between Roosendaal and Kruiningen-Yerseke
-
Update
Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to repair works.
The extra travel time is more than 60 minutes.
This will take until approximately 7:00 AM hours.Train measures
- Sprinter 6100 Roosendaal - Vlissingen is cancelled between Roosendaal and Kruiningen-Yerseke
-
Update
Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to a signal and level crossing failure.
The extra travel time is more than 60 minutes.
This will take until approximately 7:00 AM hours.Train measures
- Sprinter 6100 Roosendaal - Vlissingen is cancelled between Roosendaal and Kruiningen-Yerseke
-
Update
Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to a signal and level crossing failure.
The extra travel time is more than 60 minutes.
This will take until approximately 8:30 AM hours.Train measures
- Sprinter 6100 Roosendaal - Vlissingen is cancelled between Roosendaal and Kruiningen-Yerseke
-
Update
Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to a signal and level crossing failure.
The extra travel time is more than 60 minutes.
This will take until approximately 8:30 AM hours. -
Update
Between Bergen op Zoom and Kruiningen-Yerseke no trains are running due to a signalling and points failure.
The extra travel time is more than 60 minutes.
This will take until approximately 8:30 AM hours. -
Disruption
Between Roosendaal and Vlissingen there is a service disruption due to a signalling and points failure.
This will take until approximately 8:30 AM hours.
More about this disruption
Statistics
This disruption started at 5:29 AM on December 28, 2022 and took 2 hours, 9 minutes in total.
For statistics, this disruption is caused due to repair works.
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.