Signalling and points failure: Rotterdam-Dordrecht (16 January 2023)

  1. Disruption resolved Last update

    Between Rotterdam Centraal and Dordrecht the train traffic is fully resumed.

  2. Delays decreasing

    Between Rotterdam Centraal and Dordrecht the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 8:30 PM hours.

  3. Update

    Between Rotterdam Centraal and Dordrecht there are fewer trains running due to a signalling and points failure.
    The extra travel time may be up to 15 minutes.
    This will take until approximately 8:30 PM hours.

    Train measures

    • Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Rotterdam Centraal and Dordrecht
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag HS and Dordrecht
  4. Update

    Between Rotterdam Centraal and Dordrecht there are fewer trains running due to a signalling and points failure.
    The extra travel time may be up to 15 minutes.
    This will take until approximately 11:15 PM hours.

    Train measures

    • Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Rotterdam Centraal and Dordrecht
    • Sprinter 5000 Den Haag C. - Rotterdam C. - Dordrecht is cancelled between Den Haag HS and Dordrecht
  5. Update

    Between Rotterdam Centraal and Dordrecht there are fewer trains running due to a signalling and points failure.
    The extra travel time may be up to 15 minutes.
    This will take until approximately 11:15 PM hours.

    Train measures

    • Intercity 2400 Lelystad C. - Schiphol Airport - Rotterdam C. - Dordrecht is cancelled between Rotterdam Centraal and Dordrecht
  6. Update

    Between Rotterdam Centraal and Dordrecht there are fewer trains running due to a signal failure.
    The extra travel time may be up to 15 minutes.
    This will take until approximately 8:30 PM hours.

  7. Update

    Between Rotterdam Centraal and Rotterdam Zuid there is a service disruption due to a signal failure.
    This will take until approximately 8:30 PM hours.

  8. Disruption

    Between Rotterdam Centraal and Rotterdam Zuid there is a service disruption due to a signal failure.
    Updates will follow as more information becomes available.

More about this disruption

Statistics

This disruption started at 7:17 PM on January 16, 2023 and took 1 hour, 15 minutes in total.

For statistics, this disruption is caused due to a signalling and points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.