wisselstoring

Points failure: Lelystad-Zwolle (30 January 2023)

  1. Disruption resolved Last update

    Between Kampen Zuid and Zwolle the train traffic is fully resumed.

  2. Delays decreasing

    Between Kampen Zuid and Zwolle the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 11:45 PM hours.

    Advice

    Local buses are still running between Zwolle and Kampen Zuid.

  3. Update

    Between Kampen Zuid and Zwolle no Sprinters are running due to a points failure.
    Service is normal around 11:45 PM hours.

    Advice

    Local buses are running between Zwolle and Kampen Zuid.

    Train measures

    • Sprinter 4600 Zwolle - Schiphol Airport - Leiden C. - Den Haag C. is cancelled between Kampen Zuid and Zwolle
  4. Update

    Between Kampen Zuid and Zwolle no Sprinters are running due to a points failure.
    This will take the rest of the day.

    Advice

    Local buses are running between Zwolle and Kampen Zuid.

    Train measures

    • Sprinter 4600 Zwolle - Schiphol Airport - Leiden C. - Den Haag C. is cancelled between Kampen Zuid and Zwolle
  5. Update

    Between Kampen Zuid and Zwolle no Sprinters are running due to a points failure.
    This will take until approximately 5:30 AM on Tuesday, January 31, 2023.

    Advice

    Local buses are running between Zwolle and Kampen Zuid.

    Train measures

    • Sprinter 4600 Zwolle - Schiphol Airport - Leiden C. - Den Haag C. is cancelled between Kampen Zuid and Zwolle
  6. Update

    Between Kampen Zuid and Zwolle no Sprinters are running due to a points failure.
    This will take until approximately 9:15 PM hours.

    Advice

    Local buses are running between Zwolle and Kampen Zuid.

    Train measures

    • Sprinter 4600 Zwolle - Schiphol Airport - Leiden C. - Den Haag C. is cancelled between Kampen Zuid and Zwolle
  7. Update

    Between Kampen Zuid and Zwolle no Sprinters are running due to a points failure.
    This will take until approximately 8:00 PM hours.

    Advice

    Local buses are running between Zwolle and Kampen Zuid.

    Train measures

    • Sprinter 4600 Zwolle - Schiphol Airport - Leiden C. - Den Haag C. is cancelled between Kampen Zuid and Zwolle
  8. Update

    Between Kampen Zuid and Zwolle no Sprinters are running due to a points failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 8:00 PM hours.

    Advice

    Local buses are running between Zwolle and Kampen Zuid.

    Train measures

    • Sprinter 4600 Zwolle - Schiphol Airport - Leiden C. - Den Haag C. is cancelled between Kampen Zuid and Zwolle
  9. Update

    Between Kampen Zuid and Zwolle no Sprinters are running due to a points failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 8:00 PM hours.

    Advice

    Local buses are running between Zwolle and Kampen Zuid.

  10. Update

    Between Kampen Zuid and Zwolle no Sprinters are running due to a points failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 8:00 PM hours.

    Train measures

    • Sprinter 4600 Zwolle - Schiphol Airport - Leiden C. - Den Haag C. is cancelled between Kampen Zuid and Zwolle
  11. Disruption

    Between Kampen Zuid and Zwolle no Sprinters are running due to a points failure.
    The extra travel time is more than 60 minutes.
    This will take until approximately 8:00 PM hours.

More about this disruption

Statistics

This disruption started at 6:34 PM on January 30, 2023 and took 5 hours, 10 minutes in total.

For statistics, this disruption is caused due to a points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights