Signalling and points failure: Amsterdam-Utrecht; Utrecht-Eindhoven (13 February 2023)
-
Disruption resolved Last update
Between Utrecht Centraal and 's-Hertogenbosch the train traffic is fully resumed.
Between Amsterdam Centraal and Utrecht Centraal the train traffic is fully resumed. -
Delays decreasing
Between Utrecht Centraal and 's-Hertogenbosch the restrictions are resolved.
Between Amsterdam Centraal and Utrecht Centraal the restrictions are resolved.
Delays are decreasing.
Service is normal around 7:30 PM hours. -
Update
Between Utrecht Centraal and 's-Hertogenbosch fewer intercities are running due to a signalling and points failure.
Between Amsterdam Centraal and Utrecht Centraal fewer intercities are running due to a signalling and points failure.
This will take until approximately 7:45 PM hours.Train measures
- Intercity 800 Alkmaar - Utrecht C. - Eindhoven C. - Maastricht is cancelled between 's-Hertogenbosch and Utrecht Centraal
- Intercity 3900 Enkhuizen - Utrecht C. - Eindhoven C. - Heerlen is cancelled between Amsterdam Centraal and Eindhoven Centraal
-
Update
Between Utrecht Centraal and 's-Hertogenbosch fewer intercities are running due to a signalling and points failure.
Between Amsterdam Centraal and Utrecht Centraal fewer intercities are running due to a signalling and points failure.
This will take until approximately 9:15 PM hours.Train measures
- Intercity 800 Alkmaar - Utrecht C. - Eindhoven C. - Maastricht is cancelled between 's-Hertogenbosch and Utrecht Centraal
- Intercity 3900 Enkhuizen - Utrecht C. - Eindhoven C. - Heerlen is cancelled between Amsterdam Centraal and Eindhoven Centraal
-
Update
Between Utrecht Centraal and 's-Hertogenbosch there are fewer trains running due to a signalling and points failure.
This will take until approximately 9:15 PM hours.Train measures
- Intercity 800 Alkmaar - Utrecht C. - Eindhoven C. - Maastricht is cancelled between 's-Hertogenbosch and Utrecht Centraal
- Intercity 3900 Enkhuizen - Utrecht C. - Eindhoven C. - Heerlen is cancelled between Amsterdam Centraal and Eindhoven Centraal
-
Disruption
Between Geldermalsen and 's-Hertogenbosch there are fewer trains running due to a signalling and points failure.
This will take until approximately 9:15 PM hours.
More about this disruption
Statistics
This disruption started at 6:08 PM on February 13, 2023 and took 1 hour, 11 minutes in total.
For statistics, this disruption is caused due to a signalling and points failure.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS and NS International.
Got delayed due to this disruption? You may be reimbursed.