aanrijding

Collision: Roermond-Sittard (19 February 2023)

  1. Disruption resolved Last update

    Between Roermond and Echt the train traffic is fully resumed.

  2. Delays decreasing

    Between Roermond and Echt the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 12:30 AM hours.

  3. Update

    Between Roermond and Echt no trains are running due to a collision.
    The extra travel time is more than 60 minutes.
    This will take until approximately 1:00 AM on Monday, February 20, 2023.

    Train measures

    • Intercity 2900 Enkhuizen - Utrecht C. - Eindhoven C. - Maastricht is cancelled between Roermond and Sittard
    • Stoptrein 32400 Roermond - Maastricht - Randwyck is cancelled between Roermond and Echt
  4. Update

    Between Roermond and Echt no trains are running due to a collision.
    The extra travel time is more than 60 minutes.
    This will take until approximately 1:00 AM on Monday, February 20, 2023.

  5. Disruption

    Between Roermond and Sittard no trains are running due to a collision.
    This will take until approximately 1:00 AM on Monday, February 20, 2023.

More about this disruption

Statistics

This disruption started at 11:47 PM on February 19, 2023 and took 42 minutes in total.

For statistics, this disruption is caused due to a collision.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS and Arriva.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights