Signal and level crossing failure: Dordrecht-Roosendaal (20 March 2023)
-
Disruption resolved Last update
Between Dordrecht and Roosendaal the train traffic is fully resumed.
-
Delays decreasing
Between Dordrecht and Roosendaal the restrictions are resolved.
Delays are decreasing.
Service is normal around 4:00 PM hours. -
Update
Between Dordrecht and Roosendaal there are fewer trains running due to a signal and level crossing failure.
This will take until approximately 4:00 PM hours.Train measures
- Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Rotterdam Centraal and Roosendaal
-
Update
Between Rotterdam Centraal and Dordrecht there are fewer trains running due to a signal and level crossing failure.
Between Dordrecht and Roosendaal there are fewer trains running due to a signal and level crossing failure.
This will take until approximately 4:00 PM hours.Train measures
- Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Rotterdam Centraal and Roosendaal
-
Update
Between Rotterdam Centraal and Dordrecht there are fewer trains running due to a signal and level crossing failure.
Between Dordrecht and Roosendaal there are fewer trains running due to a signal and level crossing failure.
This will take until approximately 5:45 PM hours.Train measures
- Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Rotterdam Centraal and Roosendaal
-
Update
Between Dordrecht and Roosendaal there are fewer trains running due to a signal and level crossing failure.
Between Rotterdam Centraal and Dordrecht there are fewer trains running due to a signal and level crossing failure.
This will take until approximately 5:45 PM hours.Train measures
- Intercity 2200 Amsterdam C. - Haarlem - Rotterdam C. - Vlissingen is cancelled between Rotterdam Centraal and Roosendaal
-
Disruption
Between Dordrecht and Roosendaal there are delays and fewer trains are running due to a signal and level crossing failure.
This will take until approximately 5:45 PM hours.
More about this disruption
Statistics
This disruption started at 1:56 PM on March 20, 2023 and took 2 hours, 2 minutes in total.
For statistics, this disruption is caused due to a signal and level crossing failure.
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.