Defective railway track: Utrecht-Gouda (15 June 2023)
-
Disruption resolved Last update
Between Vleuten and Woerden the train traffic is fully resumed.
-
Delays decreasing
Between Vleuten and Woerden the restrictions are resolved.
Delays are decreasing.
Service is normal around 8:00 PM hours. -
Update
Between Vleuten and Woerden there are fewer trains running due to a defective railway track.
This will take until approximately 8:00 PM hours. -
Disruption
Between Vleuten and Woerden there are fewer trains running due to a defective railway track.
It is not known yet how long this will take.
More about this disruption
Statistics
This disruption started at 7:31 PM on June 15, 2023 and took 31 minutes in total.
For statistics, this disruption is caused due to a defective railway track.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.