herstelwerkzaamheden

Repair works: Utrecht-Arnhem; Utrecht-Veenendaal (24 July 2023)

  1. Disruption resolved Last update

    Between Utrecht Centraal and Driebergen-Zeist the train traffic is fully resumed.

  2. Update

    Between Utrecht Centraal and Driebergen-Zeist far fewer trains are running due to repair works.
    Service is normal around 5:45 PM hours.

  3. Update

    Between Utrecht Centraal and Driebergen-Zeist far fewer trains are running due to repair works.
    This will take until approximately 5:45 PM hours.

  4. Update

    Between Utrecht Centraal and Driebergen-Zeist far fewer trains are running due to repair works.
    This will take until approximately 5:45 PM hours.

    Advice

    From 17:15 fewer trains

  5. Update

    Between Utrecht Centraal and Driebergen-Zeist there are problems later today due to repair works.
    This will take until approximately 5:45 PM hours.

    Advice

    From 17:15 fewer trains

  6. Disruption

    Between Utrecht Vaartsche Rijn and Driebergen-Zeist there are problems later today due to repair works.
    This will take until approximately 5:45 PM hours.

    Advice

    From 17:15 fewer trains

More about this disruption

Statistics

This disruption started at 4:49 PM on July 24, 2023 and took 1 hour, 5 minutes in total.

For statistics, this disruption is caused due to repair works.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS and NS International.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights