sein- en overwegstoring

Signal and level crossing failure: Amersfoort-Ede-Wageningen (26 July 2023)

  1. Disruption resolved Last update

    Between Barneveld Centrum and Ede-Wageningen the train traffic is fully resumed.

  2. Delays decreasing

    Between Barneveld Centrum and Ede-Wageningen the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 2:15 PM hours.

  3. Update

    Between Barneveld Centrum and Ede-Wageningen no trains are running due to a signalling and level crossing failure.
    This will take until approximately 2:15 PM hours.

    Advice

    Local buses are running between Barneveld Centrum, Barneveld Zuid, Lunteren, Ede Centrum and Ede-Wageningen.

    Train measures

    • Stoptrein 31300 Amersfoort C./Ede-Wageningen - Ede-Wageningen/Amersfoort C. is cancelled between Barneveld Centrum and Ede-Wageningen
  4. Update

    Between Barneveld Centrum and Ede-Wageningen no trains are running due to a signalling and level crossing failure.
    This will take until approximately 2:15 PM hours.

    Advice

    Local buses are running between Barneveld Centrum, Barneveld Zuid, Lunteren, Ede Centrum and Ede-Wageningen.

    Train measures

    • Stoptrein 31300 Ede-Wageningen/Amersfoort C. - Amersfoort C./Ede-Wageningen is cancelled between Barneveld Centrum and Ede-Wageningen
  5. Update

    Between Barneveld Centrum and Ede-Wageningen no trains are running due to a signalling and level crossing failure.
    This will take until approximately 2:15 PM hours.

    Train measures

    • Stoptrein 31300 Ede-Wageningen/Amersfoort C. - Amersfoort C./Ede-Wageningen is cancelled between Barneveld Centrum and Ede-Wageningen
  6. Update

    Between Barneveld Centrum and Ede-Wageningen no trains are running due to a signalling and level crossing failure.
    This will take until approximately 2:15 PM hours.

  7. Disruption

    Between Barneveld Centrum and Lunteren there is a service disruption due to a signalling and level crossing failure.
    This will take until approximately 2:15 PM hours.

More about this disruption

Statistics

This disruption started at 12:06 PM on July 26, 2023 and took 2 hours, 7 minutes in total.

For statistics, this disruption is caused due to a signal and level crossing failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by Connexxion.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights