Signalling and points failure: Groningen-Delfzijl (29 July 2023)
-
Disruption resolved Last update
Between Stedum and Delfzijl the train traffic is fully resumed.
-
Delays decreasing
Between Stedum and Delfzijl the restrictions are resolved.
Delays are decreasing.
Service is normal around 7:00 PM hours.Advice
Local buses are still running between Stedum, Loppersum, Appingedam and Delfzijl.
-
Update
Between Stedum and Delfzijl no trains are running due to a signalling and points failure.
Service is normal around 7:30 PM hours.Advice
Local buses are running between Stedum, Loppersum, Appingedam and Delfzijl.
Train measures
- Stoptrein 37700 Delfzijl/Groningen - Groningen/Delfzijl is cancelled between Stedum and Delfzijl
-
Update
Between Stedum and Delfzijl no trains are running due to a signalling and points failure.
This will take until approximately 8:00 PM hours.Advice
Local buses are running between Stedum, Loppersum, Appingedam and Delfzijl.
Train measures
- Stoptrein 37700 Delfzijl/Groningen - Groningen/Delfzijl is cancelled between Stedum and Delfzijl
-
Update
Between Stedum and Delfzijl no trains are running due to a signalling and points failure.
The extra travel time may be up to 60 minutes.
This will take until approximately 8:00 PM hours.Advice
Local buses are running between Stedum, Loppersum, Appingedam and Delfzijl.
Train measures
- Stoptrein 37700 Delfzijl/Groningen - Groningen/Delfzijl is cancelled between Stedum and Delfzijl
-
Update
Between Stedum and Delfzijl no trains are running due to a signalling and points failure.
The extra travel time may be up to 60 minutes.
This will take until approximately 7:30 PM hours.Advice
Local buses are running between Stedum, Loppersum, Appingedam and Delfzijl.
Train measures
- Stoptrein 37700 Delfzijl/Groningen - Groningen/Delfzijl is cancelled between Stedum and Delfzijl
-
Update
Between Stedum and Delfzijl no trains are running due to a signalling and points failure.
The extra travel time may be up to 60 minutes.
This will take until approximately 6:30 PM hours.Advice
Local buses are running between Stedum, Loppersum, Appingedam and Delfzijl.
Train measures
- Stoptrein 37700 Delfzijl/Groningen - Groningen/Delfzijl is cancelled between Stedum and Delfzijl
-
Update
Between Stedum and Delfzijl no trains are running due to a signalling and points failure.
The extra travel time may be up to 60 minutes.
This will take until approximately 5:00 PM hours.Advice
Local buses are running between Stedum, Loppersum, Appingedam and Delfzijl.
Train measures
- Stoptrein 37700 Delfzijl/Groningen - Groningen/Delfzijl is cancelled between Stedum and Delfzijl
-
Update
Between Stedum and Delfzijl no trains are running due to a signalling and points failure.
The extra travel time may be up to 60 minutes.
This will take until approximately 4:30 PM hours.Advice
Local buses are running between Stedum, Loppersum, Appingedam and Delfzijl.
Train measures
- Stoptrein 37700 Delfzijl/Groningen - Groningen/Delfzijl is cancelled between Stedum and Delfzijl
-
Update
Between Stedum and Delfzijl no trains are running due to a signalling and points failure.
The extra travel time may be up to 60 minutes.
This will take until approximately 4:00 PM hours.Advice
Local buses are running between Stedum, Loppersum, Appingedam and Delfzijl.
Train measures
- Stoptrein 37700 Delfzijl/Groningen - Groningen/Delfzijl is cancelled between Stedum and Delfzijl
-
Update
Between Stedum and Delfzijl no trains are running due to a signalling and points failure.
The extra travel time may be up to 60 minutes.
This will take until approximately 4:30 PM hours.Train measures
- Stoptrein 37700 Delfzijl/Groningen - Groningen/Delfzijl is cancelled between Stedum and Delfzijl
-
Update
Between Stedum and Delfzijl no trains are running due to a signalling and points failure.
The extra travel time may be up to 60 minutes.
This will take until approximately 4:00 PM hours.Train measures
- Stoptrein 37700 Delfzijl/Groningen - Groningen/Delfzijl is cancelled between Stedum and Delfzijl
-
Update
Between Stedum and Delfzijl no trains are running due to a signalling and points failure.
The extra travel time may be up to 60 minutes.
This will take until approximately 4:00 PM hours.Train measures
- Stoptrein 37700 Groningen/Delfzijl - Delfzijl/Groningen is cancelled between Stedum and Delfzijl
-
Update
Between Stedum and Delfzijl no trains are running due to a signalling and points failure.
The extra travel time may be up to 60 minutes.
This will take until approximately 4:00 PM hours. -
Disruption
Between Groningen and Loppersum there is a service disruption due to a signalling and points failure.
This will take until approximately 4:00 PM hours.
More about this disruption
Statistics
This disruption started at 1:47 PM on July 29, 2023 and took 5 hours, 12 minutes in total.
For statistics, this disruption is caused due to a signalling and points failure.
Operators
This disruption affects trains operated by Arriva.
Got delayed due to this disruption? You may be reimbursed.