seinstoring

Signal failure: Den Haag-Rotterdam-Eindhoven (HSL) (31 July 2023)

  1. Disruption resolved Last update

    Between Rotterdam Centraal and Breda the train traffic is fully resumed.

  2. Delays decreasing

    Between Rotterdam Centraal and Breda the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 11:30 AM hours.

  3. Update

    Between Rotterdam Centraal and Breda fewer Intercity direct trains are running due to a signal failure.
    Service is normal around 11:30 AM hours.

    Train measures

    • Intercity 1100 Den Haag C./Eindhoven C. - Eindhoven C./Den Haag C. is cancelled between Rotterdam Centraal and Breda
  4. Update

    Between Rotterdam Centraal and Breda fewer Intercity direct trains are running due to a signal failure.
    Service is normal around 11:45 AM hours.

    Train measures

    • Intercity 1100 Den Haag C./Eindhoven C. - Eindhoven C./Den Haag C. is cancelled between Rotterdam Centraal and Breda
  5. Update

    Between Rotterdam Centraal and Breda fewer Intercity direct trains are running due to a signal failure.
    This will take until approximately 12:15 PM hours.

    Train measures

    • Intercity 1100 Den Haag C./Eindhoven C. - Eindhoven C./Den Haag C. is cancelled between Rotterdam Centraal and Breda
  6. Update

    Between Rotterdam Centraal and Breda there are fewer trains running due to a signal failure.
    This will take until approximately 12:15 PM hours.

    Train measures

    • Intercity 1100 Eindhoven C./Den Haag C. - Den Haag C./Eindhoven C. is cancelled between Rotterdam Centraal and Breda
  7. Update

    Between Rotterdam Centraal and Breda there are fewer trains running due to a signal failure.
    This will take until approximately 12:15 PM hours.

  8. Update

    Between Rotterdam Centraal and Dordrecht there are fewer trains running due to a signal failure.
    This will take until approximately 12:15 PM hours.

  9. Disruption

    From and to Rotterdam Centraal there is a service disruption due to a signal failure.
    This will take until approximately 12:15 PM hours.

More about this disruption

Statistics

This disruption started at 9:49 AM on July 31, 2023 and took 1 hour, 38 minutes in total.

For statistics, this disruption is caused due to a signal failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS and NS International.

Got delayed due to this disruption? You may be reimbursed.

Refunds and passenger rights