Signalling and points failure: Zwolle-Enschede (29 August 2023)

  1. Disruption resolved Last update

    Between Raalte and Enschede the train traffic is fully resumed.

  2. Delays decreasing

    Between Raalte and Enschede the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 6:35 PM hours.

  3. Delays decreasing

    Between Raalte and Enschede the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 6:15 PM hours.

  4. Update

    Between Raalte and Enschede no intercities are running due to a signalling and points failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 6:45 PM hours.

    Train measures

    • Sprinter 7000 Enschede/Apeldoorn - Apeldoorn/Enschede is cancelled between Rijssen and Almelo
    • Sprinter 7900-7995 Enschede/Zwolle - Zwolle/Enschede is cancelled between Wierden and Almelo
    • Intercity 17900 Enschede/Zwolle - Zwolle/Enschede is cancelled between Enschede and Zwolle
  5. Update

    Between Raalte and Enschede no intercities are running due to a signalling and points failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 6:30 PM hours.

    Train measures

    • Sprinter 7000 Apeldoorn/Enschede - Enschede/Apeldoorn is cancelled between Rijssen and Almelo
    • Sprinter 7900-7995 Zwolle/Enschede - Enschede/Zwolle is cancelled between Wierden and Almelo
    • Intercity 17900 Zwolle/Enschede - Enschede/Zwolle is cancelled between Enschede and Zwolle
  6. Update

    Between Raalte and Enschede no intercities are running due to a signalling and points failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 6:30 PM hours.

  7. Update

    Between Wierden and Almelo there are delays and fewer trains are running due to a signalling and points failure.
    This will take until approximately 6:30 PM hours.

  8. Update

    Between Wierden and Almelo there are delays and fewer trains are running due to a signalling and points failure.
    This will take until approximately 7:30 PM hours.

  9. Update

    Between Wierden and Almelo there are delays and fewer trains are running due to a signalling and points failure.
    This will take until approximately 6:30 PM hours.

  10. Disruption resolved

    Between Wierden and Almelo the train traffic is fully resumed.
    Between Almelo and Mariënberg the train traffic is fully resumed.

  11. Disruption

    Between Wierden and Almelo there is a service disruption due to a signalling and points failure.
    Between Almelo and Mariënberg there is a service disruption due to a signalling and points failure.
    This will take until approximately 6:45 PM hours.

More about this disruption

Statistics

This disruption started at 4:30 PM on August 29, 2023 and took 2 hours, 3 minutes in total.

For statistics, this disruption is caused due to a signalling and points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS, NS International, Keolis and Blauwnet.

Got delayed due to this disruption? You may be reimbursed.