sein- en wisselstoring

Signalling and points failure: Leiden-Duivendrecht-Lelystad (6 September 2023)

  1. Disruption resolved Last update

    Between Almere Centrum and Leiden Centraal the train traffic is fully resumed.

  2. Delays decreasing

    Between Almere Centrum and Leiden Centraal the restrictions are resolved.
    Delays are decreasing.
    Service is normal around 10:45 AM hours.

  3. Update

    Between Almere Centrum and Leiden Centraal no intercities are running due to a signalling and points failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 10:30 AM hours.

    Train measures

    • Intercity 700 Den Haag C./Groningen - Groningen/Den Haag C. is cancelled between Almere Centrum and Den Haag Centraal
    • Intercity 1800 Den Haag C./Leeuwarden - Leeuwarden/Den Haag C. is cancelled between Almere Centrum and Den Haag Centraal
    • Intercity 2400 Lelystad C./Dordrecht - Dordrecht/Lelystad C. is cancelled between Lelystad Centrum and Leiden Centraal
  4. Update

    Between Almere Centrum and Leiden Centraal no intercities are running due to a signalling and points failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 10:15 AM hours.

    Train measures

    • Intercity 2400 Dordrecht/Lelystad C. - Lelystad C./Dordrecht is cancelled between Lelystad Centrum and Leiden Centraal
  5. Update

    From and to Schiphol Airport there are fewer trains running due to a signalling and points failure.
    This will take until approximately 10:30 AM hours.

    Train measures

    • Intercity 700 Groningen/Den Haag C. - Den Haag C./Groningen is cancelled between Almere Centrum and Den Haag Centraal
    • Intercity 1800 Leeuwarden/Den Haag C. - Den Haag C./Leeuwarden is cancelled between Almere Centrum and Den Haag Centraal
    • Intercity 2400 Dordrecht/Lelystad C. - Lelystad C./Dordrecht is cancelled between Lelystad Centrum and Leiden Centraal
  6. Update

    From and to Schiphol Airport there are fewer trains running due to a signalling and points failure.
    This will take until approximately 10:30 AM hours.

    Train measures

    • Intercity 700 Groningen/Den Haag C. - Den Haag C./Groningen is cancelled between Almere Centrum and Den Haag Centraal
    • Intercity 1600 Enschede/Schiphol Airport - Schiphol Airport/Enschede is cancelled between Schiphol Airport and Hilversum
    • Intercity 1800 Leeuwarden/Den Haag C. - Den Haag C./Leeuwarden is cancelled between Almere Centrum and Den Haag Centraal
    • Intercity 2400 Dordrecht/Lelystad C. - Lelystad C./Dordrecht is cancelled between Lelystad Centrum and Leiden Centraal
    • Intercity 3100 Nijmegen/Schiphol Airport - Schiphol Airport/Nijmegen is cancelled between Amsterdam Bijlmer ArenA and Schiphol Airport
  7. Update

    From and to Schiphol Airport far fewer trains are running due to a signalling and points failure.
    This will take until approximately 10:30 AM hours.

    Train measures

    • Intercity 700 Groningen/Den Haag C. - Den Haag C./Groningen is cancelled between Almere Centrum and Den Haag Centraal
    • Intercity 1600 Enschede/Schiphol Airport - Schiphol Airport/Enschede is cancelled between Schiphol Airport and Hilversum
    • Intercity 1800 Leeuwarden/Den Haag C. - Den Haag C./Leeuwarden is cancelled between Almere Centrum and Den Haag Centraal
    • Intercity 2400 Dordrecht/Lelystad C. - Lelystad C./Dordrecht is cancelled between Lelystad Centrum and Leiden Centraal
    • Intercity 3100 Nijmegen/Schiphol Airport - Schiphol Airport/Nijmegen is cancelled between Amsterdam Bijlmer ArenA and Schiphol Airport
    • Intercity 3500 Venlo/Schiphol Airport - Schiphol Airport/Venlo is cancelled between Amsterdam Zuid and Schiphol Airport
    • Sprinter 4300 Oostvaarders/Hoofddorp - Hoofddorp/Oostvaarders is cancelled between Hoofddorp and Almere Oostvaarders
    • Intercity 11600 Schothorst/Schiphol Airport - Schiphol Airport/Schothorst is cancelled between Schiphol Airport and Hilversum
  8. Update

    From and to Schiphol Airport far fewer trains are running due to a signalling and points failure.
    This will take until approximately 12:30 PM hours.

    Train measures

    • Intercity 700 Groningen/Den Haag C. - Den Haag C./Groningen is cancelled between Almere Centrum and Den Haag Centraal
    • Intercity 1600 Enschede/Schiphol Airport - Schiphol Airport/Enschede is cancelled between Schiphol Airport and Hilversum
    • Intercity 1800 Leeuwarden/Den Haag C. - Den Haag C./Leeuwarden is cancelled between Almere Centrum and Den Haag Centraal
    • Intercity 2400 Dordrecht/Lelystad C. - Lelystad C./Dordrecht is cancelled between Lelystad Centrum and Leiden Centraal
    • Intercity 3100 Nijmegen/Schiphol Airport - Schiphol Airport/Nijmegen is cancelled between Amsterdam Bijlmer ArenA and Schiphol Airport
    • Intercity 3500 Venlo/Schiphol Airport - Schiphol Airport/Venlo is cancelled between Amsterdam Zuid and Schiphol Airport
    • Sprinter 4300 Oostvaarders/Hoofddorp - Hoofddorp/Oostvaarders is cancelled between Hoofddorp and Almere Oostvaarders
    • Intercity 11600 Schothorst/Schiphol Airport - Schiphol Airport/Schothorst is cancelled between Schiphol Airport and Hilversum
  9. Update

    From and to Schiphol Airport far fewer trains are running due to a signalling and points failure.
    This will take until approximately 10:30 AM hours.

    Train measures

    • Intercity 700 Groningen/Den Haag C. - Den Haag C./Groningen is cancelled between Almere Centrum and Den Haag Centraal
    • Intercity 1600 Enschede/Schiphol Airport - Schiphol Airport/Enschede is cancelled between Schiphol Airport and Hilversum
    • Intercity 1800 Leeuwarden/Den Haag C. - Den Haag C./Leeuwarden is cancelled between Almere Centrum and Den Haag Centraal
    • Intercity 2400 Dordrecht/Lelystad C. - Lelystad C./Dordrecht is cancelled between Lelystad Centrum and Leiden Centraal
    • Intercity 3100 Nijmegen/Schiphol Airport - Schiphol Airport/Nijmegen is cancelled between Amsterdam Bijlmer ArenA and Schiphol Airport
    • Intercity 3500 Venlo/Schiphol Airport - Schiphol Airport/Venlo is cancelled between Amsterdam Zuid and Schiphol Airport
    • Sprinter 4300 Oostvaarders/Hoofddorp - Hoofddorp/Oostvaarders is cancelled between Hoofddorp and Almere Oostvaarders
    • Intercity 11600 Schothorst/Schiphol Airport - Schiphol Airport/Schothorst is cancelled between Schiphol Airport and Hilversum
  10. Update

    From and to Schiphol Airport far fewer trains are running due to a signalling and points failure.
    This will take until approximately 10:15 AM hours.

    Train measures

    • Intercity 700 Groningen/Den Haag C. - Den Haag C./Groningen is cancelled between Almere Centrum and Den Haag Centraal
    • Intercity 1600 Enschede/Schiphol Airport - Schiphol Airport/Enschede is cancelled between Schiphol Airport and Hilversum
    • Intercity 1800 Leeuwarden/Den Haag C. - Den Haag C./Leeuwarden is cancelled between Almere Centrum and Den Haag Centraal
    • Intercity 2400 Dordrecht/Lelystad C. - Lelystad C./Dordrecht is cancelled between Lelystad Centrum and Leiden Centraal
    • Intercity 3100 Nijmegen/Schiphol Airport - Schiphol Airport/Nijmegen is cancelled between Amsterdam Bijlmer ArenA and Schiphol Airport
    • Intercity 3500 Venlo/Schiphol Airport - Schiphol Airport/Venlo is cancelled between Amsterdam Zuid and Schiphol Airport
    • Sprinter 4300 Oostvaarders/Hoofddorp - Hoofddorp/Oostvaarders is cancelled between Hoofddorp and Almere Oostvaarders
    • Intercity 11600 Schothorst/Schiphol Airport - Schiphol Airport/Schothorst is cancelled between Schiphol Airport and Hilversum
  11. Update

    From and to Schiphol Airport far fewer trains are running due to a signalling and points failure.
    This will take until approximately 10:15 AM hours.

    Train measures

    • Intercity 700 Groningen/Den Haag C. - Den Haag C./Groningen is cancelled between Almere Centrum and Den Haag Centraal
    • Intercity 1600 Enschede/Schiphol Airport - Schiphol Airport/Enschede is cancelled between Schiphol Airport and Hilversum
    • Intercity 1800 Leeuwarden/Den Haag C. - Den Haag C./Leeuwarden is cancelled between Almere Centrum and Den Haag Centraal
    • Intercity 2400 Dordrecht/Lelystad C. - Lelystad C./Dordrecht is cancelled between Lelystad Centrum and Leiden Centraal
    • Intercity 3100 Nijmegen/Schiphol Airport - Schiphol Airport/Nijmegen is cancelled between Amsterdam Bijlmer ArenA and Schiphol Airport
    • Intercity 3500 Venlo/Schiphol Airport - Schiphol Airport/Venlo is cancelled between Amsterdam Zuid and Schiphol Airport
    • Sprinter 4300 Oostvaarders/Hoofddorp - Hoofddorp/Oostvaarders is cancelled between Hoofddorp and Almere Oostvaarders
  12. Update

    Between Almere Centrum and Leiden Centraal no intercities are running due to a signalling and points failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 10:15 AM hours.

    Train measures

    • Intercity 2400 Dordrecht/Lelystad C. - Lelystad C./Dordrecht is cancelled between Lelystad Centrum and Leiden Centraal
  13. Update

    Between Almere Centrum and Leiden Centraal no intercities are running due to a signalling and points failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 10:15 AM hours.

  14. Update

    Between Lelystad Centrum and Leiden Centraal no intercities are running due to a signalling and points failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 10:15 AM hours.

  15. Update

    Between Almere Centrum and Leiden Centraal no intercities are running due to a signalling and points failure.
    The extra travel time may be up to 30 minutes.
    This will take until approximately 10:15 AM hours.

  16. Update

    Between Amsterdam Zuid and Schiphol Airport there are delays and fewer trains are running due to a signalling and points failure.
    This will take until approximately 10:15 AM hours.

  17. Disruption

    Between Amsterdam Sloterdijk and Schiphol Airport there is a service disruption due to a signalling and points failure.
    Between Amsterdam Zuid and Schiphol Airport there is a service disruption due to a signalling and points failure.
    This will take until approximately 10:15 AM hours.

More about this disruption

Statistics

This disruption started at 7:18 AM on September 6, 2023 and took 3 hours, 14 minutes in total.

For statistics, this disruption is caused due to a signalling and points failure.

Affected lines

The following lines are affected by this disruption:

Operators

This disruption affects trains operated by NS.

Got delayed due to this disruption? You may be reimbursed.