Engineering works: Den Haag-Rotterdam (22 November 2023)
-
Disruption resolved Last update
Between Delft and Schiedam Centrum the train traffic is fully resumed.
-
Disruption
Between Delft and Schiedam Centrum no trains are running due to engineering works.
This will take until approximately 5:15 AM hours.Advice
Buses are running between Delft and Schiedam Centrum.
Train measures
- Intercity 1400 Rotterdam C./Rotterdam C. - Utrecht C./Utrecht C. is cancelled between Delft and Schiedam Centrum
- Intercity 2200 Amsterdam C./Vlissingen - Vlissingen/Amsterdam C. is cancelled between Delft and Schiedam Centrum
More about this disruption
Statistics
This disruption started at 1:01 AM on November 22, 2023 and took 4 hours, 9 minutes in total.
For statistics, this disruption is caused due to engineering works.
Affected lines
The following lines are affected by this disruption:
Operators
This disruption affects trains operated by NS.
Got delayed due to this disruption? You may be reimbursed.